Doubtnut Promotions Sticky

A, b and C can alone complete a work in 10, 12 and 15 days
respectively. A and C started the work and after working for
4 days, A left and B joined. In how many days the total work
was completed ?

A

659days

B

629days

C

6 days

D

549days

Video Solution
Text Solution
Verified by Experts

The correct Answer is:(b)


(A+C)=110+115+16 They worked for 4 days so did
16×423 of work
Remaining work =123=13
Now A left, B and C working
(B+C)=(112+115)=960=320. They worked for x
days and completed 1.3ed of work so 320×x=13,
So x=209 days
Total =4+209=569=629 day

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A, B and C can alone complete a work in 15, 25 and 30 days
    respectively. A and B started the work and after some days A
    is replaced by C. Now the work is completed in a further of
    6 4/11 days. How much of the total work did B did ?

    A411
    B415
    C512
    D511
  • Question 2 - Select One

    A, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?

    A2
    B52
    C114
    D95
  • Question 3 - Select One

    A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?

    A5
    B4
    C3
    D6