A, b and C can alone complete a work in 10, 12 and 15 days
respectively. A and C started the work and after working for
4 days, A left and B joined. In how many days the total work
was completed ?
659days
629days
6 days
549days
The correct Answer is:(b)
(A+C)=110+115+16 They worked for 4 days so did
16×423 of work
Remaining work =1−23=13
Now A left, B and C working
(B+C)=(112+115)=960=320. They worked for x
days and completed 1.3ed of work so 320×x=13,
So x=209 days
Total =4+209=569=629 day
Topper's Solved these Questions
Similar Questions
A can do a piece of work in 20 days and B can do same work in 25 days. Both A and B start the work and after 8 days A left. In how many days will the total work be completed ?
View SolutionA, B and C can do a piece of work individually in 8, 12 and 15 days respectively. A and B start working, but A quits after working for 2 days. After this, C joins B till the completion of work. In how many days will the work be completed ?
View Solution
Knowledge Check
- Question 1 - Select One
A, B and C can alone complete a work in 15, 25 and 30 days
respectively. A and B started the work and after some days A
is replaced by C. Now the work is completed in a further of
6 4/11 days. How much of the total work did B did ?A411B415C512D511 - Question 2 - Select One
A, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?
A2B52C114D95 - Question 3 - Select One
A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?
A5B4C3D6
A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?
View SolutionA,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed? 4 b. 15 c. 7 d. 8
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?
View SolutionA,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
View Solution