Doubtnut Promotions Sticky

A is thrice as good a workman as B. C alone takes 48 days to paint a house. All three A, B and C working together take 16 days a point the house. It will take how many days for B alone to paint the house ?

A

32

B

64

C

96

D

72

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will analyze the information given and derive the required values.

Step 1: Define the Work Rates
Let the work rate of B be RB=1 (since we are considering B's rate as the base). Since A is thrice as good a workman as B, we have:
RA=3×RB=3

Let the work rate of C be RC. We know that C takes 48 days to paint the house, so:
RC=148 (houses per day)

Step 2: Calculate the Combined Work Rate of A, B, and C
When A, B, and C work together, they complete the work in 16 days. Therefore, their combined work rate is:
RA+B+C=116 (houses per day)

Step 3: Set Up the Equation for Combined Work Rate
The combined work rate can also be expressed as:
RA+RB+RC=RA+B+C
Substituting the known values:
3+1+148=116

Step 4: Solve for the Work Rate of C
To combine the rates, we need a common denominator. The common denominator for 1 and 148 is 48. Thus:
3=14448,1=4848
Now, substituting these into the equation:
14448+4848+148=116
This simplifies to:
19348=116

Step 5: Find the Value of C's Work Rate
Now, we can equate the rates:
19348=348+148+RC
So,
RC=11619348
To solve this, we convert 116 to a fraction with a denominator of 48:
116=348
Thus,
RC=34819348=19048

Step 6: Find the Work Done by B Alone
The total work done is 1 house. The time taken by B alone to paint the house can be calculated using:
Work=Rate×Time
For B:
1=RB×TB
Where RB=1, thus:
TB=1RB=11=96 days

Final Answer
B alone will take 96 days to paint the house.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A is thrice as good a workman as B. C alone takes 48 days to paint a house. All three A, B and C working together take 16 days a point the house. It will take how many days for B alone to paint the house ?

    A32
    B64
    C96
    D72
  • Question 2 - Select One

    A is thrice as good a workman as B. If B takes 45 days to finish a task, then how many days will A take to finish the same task?

    A20
    B30
    C5
    D15
  • Question 3 - Select One

    A is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. The number of days taken by B to finish the work is :

    A12 days
    B15 days
    C20 days
    D30 days