A is thrice as good a workman as B. C alone takes 48 days to paint a house. All three A, B and C working together take 16 days a point the house. It will take how many days for B alone to paint the house ?
32
64
96
72
The correct Answer is:C
To solve the problem step by step, we will analyze the information given and derive the required values.
Step 1: Define the Work Rates
Let the work rate of B be RB=1 (since we are considering B's rate as the base). Since A is thrice as good a workman as B, we have:
RA=3×RB=3
Let the work rate of C be RC. We know that C takes 48 days to paint the house, so:
RC=148 (houses per day)
Step 2: Calculate the Combined Work Rate of A, B, and C
When A, B, and C work together, they complete the work in 16 days. Therefore, their combined work rate is:
RA+B+C=116 (houses per day)
Step 3: Set Up the Equation for Combined Work Rate
The combined work rate can also be expressed as:
RA+RB+RC=RA+B+C
Substituting the known values:
3+1+148=116
Step 4: Solve for the Work Rate of C
To combine the rates, we need a common denominator. The common denominator for 1 and 148 is 48. Thus:
3=14448,1=4848
Now, substituting these into the equation:
14448+4848+148=116
This simplifies to:
19348=116
Step 5: Find the Value of C's Work Rate
Now, we can equate the rates:
19348=348+148+RC
So,
RC=116−19348
To solve this, we convert 116 to a fraction with a denominator of 48:
116=348
Thus,
RC=348−19348=−19048
Step 6: Find the Work Done by B Alone
The total work done is 1 house. The time taken by B alone to paint the house can be calculated using:
Work=Rate×Time
For B:
1=RB×TB
Where RB=1, thus:
TB=1RB=11=96 days
Final Answer
B alone will take 96 days to paint the house.
Let the work rate of B be RB=1 (since we are considering B's rate as the base). Since A is thrice as good a workman as B, we have:
RA=3×RB=3
RC=148 (houses per day)
When A, B, and C work together, they complete the work in 16 days. Therefore, their combined work rate is:
RA+B+C=116 (houses per day)
The combined work rate can also be expressed as:
RA+RB+RC=RA+B+C
Substituting the known values:
3+1+148=116
To combine the rates, we need a common denominator. The common denominator for 1 and 148 is 48. Thus:
3=14448,1=4848
Now, substituting these into the equation:
14448+4848+148=116
This simplifies to:
19348=116
Now, we can equate the rates:
19348=348+148+RC
So,
RC=116−19348
To solve this, we convert 116 to a fraction with a denominator of 48:
116=348
Thus,
RC=348−19348=−19048
The total work done is 1 house. The time taken by B alone to paint the house can be calculated using:
Work=Rate×Time
For B:
1=RB×TB
Where RB=1, thus:
TB=1RB=11=96 days
B alone will take 96 days to paint the house.
Topper's Solved these Questions
Similar Questions
A is twice as good a workman as B and C is thrice as good a workman as B and C is thrice as good a workman as B . If A, B and C together can complete a work in 2 days , then in how many days can A alone complete the work ?
View SolutionIf m persons can paint a house in d days, how many days will it take for (m + 2) persons to paint the same house?
View Solution
Knowledge Check
- Question 1 - Select One
A is thrice as good a workman as B. C alone takes 48 days to paint a house. All three A, B and C working together take 16 days a point the house. It will take how many days for B alone to paint the house ?
A32B64C96D72 - Question 2 - Select One
A is thrice as good a workman as B. If B takes 45 days to finish a task, then how many days will A take to finish the same task?
A20B30C5D15 - Question 3 - Select One
A is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. The number of days taken by B to finish the work is :
A12 daysB15 daysC20 daysD30 days
A is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. The number of days taken by B to finish the work is :
View SolutionA is twice as good a workman as B and therefore A takes 6 days less than B to finish the work individually. If A and B working complete together the work in 4 days, then how many days are required by B to complete the work alone?
View SolutionA is twice as good a workman as B and therefore A takes 6 days less than B to finish the work individually. If A and B working complete together the work in 4 days, then how many days are required by B to complete the work alone?
View SolutionB can do a job twice as fast as A and half as fast as C.A.B. and C together take 16 days to complete it. In many days can C alone complete it ?
View SolutionA alone takes 4 more days to complete a work, in that time A and B can complete it together and B alone takes 16 more days to complete the same. In how many days they will do it together?
View Solution