Doubtnut Promotions Sticky

The ratio of the efficiencies of A, B, C is 7:5:4. Working togehter, they can finish a work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone.

A

56

B

63

C

49

D

60

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will follow the given information about the efficiencies of A, B, and C, and how they work together.

Step 1: Determine the total efficiency of A, B, and C
The efficiencies of A, B, and C are given in the ratio 7:5:4.

Let the efficiencies be:
- Efficiency of A = 7x
- Efficiency of B = 5x
- Efficiency of C = 4x

Total efficiency of A, B, and C together:
Total Efficiency=7x+5x+4x=16x

Step 2: Calculate the total work done
It is given that A, B, and C together can finish the work in 35 days.

Using the formula:
Total Work=Total Efficiency×Time
We can calculate the total work:
Total Work=16x×35=560x

Step 3: Calculate the work done by A and B in 28 days
Now, A and B work together for 28 days. Their combined efficiency is:
Efficiency of A and B=7x+5x=12x

The work done by A and B in 28 days is:
Work done by A and B=Efficiency of A and B×Time
Work done=12x×28=336x

Step 4: Calculate the remaining work
Now, we can find the remaining work after A and B have worked for 28 days:
Remaining Work=Total WorkWork done by A and B
Remaining Work=560x336x=224x

Step 5: Calculate the time taken by C to complete the remaining work
C will complete the remaining work alone. The efficiency of C is 4x.

Using the formula for time:
Time=WorkEfficiency
We can calculate the time taken by C:
Time taken by C=224x4x=56 days

Final Answer
C will take 56 days to complete the remaining work.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    The ratio of the efficiencies of A, B and C is 7:5:4. Working together, they can finish work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone:
    A, B और C की कार्य क्षमता का अनुपात 7 : 5 : 4 है | एक साथ कार्य करते हुए, वे किसी कार्य को 35 दिनों में समाप्त कर सकते हैं | A और B एक साथ 28 दिनों तक कार्य करते हैं | C शेष कार्य कितने दिनों में पूरा करेगा ?

    A60
    B63
    C56
    D49
  • Question 2 - Select One

    To do a certain work the ratio of the efficincies of A, B and C is 7:5:6. Working together they can complete the same work in 35 days. B and C work together for 21 days. The remaining work will be completed by A alone in:

    A60 days
    B57 days
    C54 days
    D50 days
  • Question 3 - Select One

    The ratio of the efficiencies of A, B and C is 3: 5:1. Working together, they can complete a piece of work in 5 days. A and B work together for 3 days. The remaining work will be completed by C alone in?

    A18 days
    B24 days
    C21 days
    D15 days