Doubtnut Promotions Sticky

The efficiencies of A, B and C are in the ratio 5: 3: 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in:

A

30 days

B

32 days

C

36 days

D

40 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the efficiencies of A, B, and C
Let the efficiencies of A, B, and C be represented as:
- Efficiency of A = 5K
- Efficiency of B = 3K
- Efficiency of C = 8K

Step 2: Calculate the total efficiency
The total efficiency when A, B, and C work together is:
Total Efficiency=5K+3K+8K=16K

Step 3: Calculate the total work
Since A, B, and C can complete the work together in 30 days, the total work can be calculated as:
Total Work=Total Efficiency×Time=16K×30=480K units

Step 4: Calculate the work done by A and B in 20 days
The combined efficiency of A and B is:
Efficiency of A and B=5K+3K=8K
The work done by A and B in 20 days is:
Work Done by A and B=Efficiency of A and B×Time=8K×20=160K units

Step 5: Calculate the remaining work
The remaining work after A and B have worked for 20 days is:
Remaining Work=Total WorkWork Done by A and B=480K160K=320K units

Step 6: Calculate the time taken by C to complete the remaining work
C's efficiency is 8K. The time taken by C to complete the remaining work is:
Time Taken by C=Remaining WorkEfficiency of C=320K8K=40 days

Final Answer
C will complete the remaining work in 40 days.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    The ratio of the efficiencies of A, B and C is 3: 5:1. Working together, they can complete a piece of work in 5 days. A and B work together for 3 days. The remaining work will be completed by C alone in?

    A18 days
    B24 days
    C21 days
    D15 days
  • Question 2 - Select One

    The ratio of the efficiencies of A, B and C to do a certain work is 7:3:5. Working together, they can complete the work in 21 days. A and C worked together for 5 days. The remaining work will be completed by B alone in :

    A54 days
    B45 days
    C60 days
    D85 days
  • Question 3 - Select One

    The ratio of the efficiencies of A, B and C is 7:5:4. Working together, they can finish work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone:
    A, B और C की कार्य क्षमता का अनुपात 7 : 5 : 4 है | एक साथ कार्य करते हुए, वे किसी कार्य को 35 दिनों में समाप्त कर सकते हैं | A और B एक साथ 28 दिनों तक कार्य करते हैं | C शेष कार्य कितने दिनों में पूरा करेगा ?

    A60
    B63
    C56
    D49