Doubtnut Promotions Sticky

To do a certain work, A and B work on alternate days, with B beginning the work on the first day. A can finish the work alone in 48 days. If the work gets completed in 1113 days, then B alone can finish 4 times the same work in:

A

24 days

B

32 days

C

27 days

D

30 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem, we need to determine how long it would take B to complete 4 times the work, given that A and B work on alternate days and the total work is completed in 11 1/3 days.

1. Determine the Work Done by A in One Day:
- A can complete the work in 48 days.
- Therefore, the work done by A in one day = 148 of the work.

Hint: To find the work done in one day, take the reciprocal of the total days taken to complete the work.

2. Determine the Work Done by B in One Day:
- Let the work done by B in one day be 1b.
- Since A and B work on alternate days, B works on the 1st, 3rd, 5th, etc., days, while A works on the 2nd, 4th, 6th, etc.

3. Calculate the Total Days Worked:
- The total time taken to complete the work is 1113 days, which can be converted to an improper fraction:
- 1113=343 days.

4. Determine the Number of Days Each Works:
- In 1113 days, there are 6 complete days (3 days for A and 3 days for B) and 1 extra day (B works on the 1st day).
- Therefore, A works for 5 days and B works for 6 days.

5. Set Up the Equation for Total Work Done:
- Total work done = Work done by A + Work done by B
- Total Work=5×148+6×1b=1 (since they complete the whole work)
- This simplifies to:
548+6b=1

6. Solve for B's Work Rate:
- Rearranging gives:
6b=1548
- Convert 1 to a fraction with a denominator of 48:
1=48486b=48548=4348
- Cross-multiplying gives:
6×48=43b288=43bb=28843

7. Calculate the Time B Takes to Complete 4 Times the Work:
- If B can complete the work in 28843 days, then to complete 4 times the work:
Time for B to complete 4 times the work=4×28843=115243 days

Final Answer:
B alone can finish 4 times the same work in 115243 days, which is approximately 26.74 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can finish a work in 15 days, B and C in 20 days, while C and A in 30 days, then A alone can finish the work in

    A40 days
    B24 days
    C120 days
    D13 days
  • Question 2 - Select One

    A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :

    A9
    B8
    C10
    D6
  • Question 3 - Select One

    A and B complete a work in 16 days, while A alone can finish that work in 24 days. In how many days, B alone can finish that work ?

    A56 days
    B48 days
    C36 days
    D64 days