To do a certain work, A and B work on alternate days, with B beginning the work on the first day. A can finish the work alone in 48 days. If the work gets completed in 1113 days, then B alone can finish 4 times the same work in:
24 days
32 days
27 days
30 days
The correct Answer is:C
To solve the problem, we need to determine how long it would take B to complete 4 times the work, given that A and B work on alternate days and the total work is completed in 11 1/3 days.
1. Determine the Work Done by A in One Day:
- A can complete the work in 48 days.
- Therefore, the work done by A in one day = 148 of the work.
Hint: To find the work done in one day, take the reciprocal of the total days taken to complete the work.
2. Determine the Work Done by B in One Day:
- Let the work done by B in one day be 1b.
- Since A and B work on alternate days, B works on the 1st, 3rd, 5th, etc., days, while A works on the 2nd, 4th, 6th, etc.
3. Calculate the Total Days Worked:
- The total time taken to complete the work is 1113 days, which can be converted to an improper fraction:
- 1113=343 days.
4. Determine the Number of Days Each Works:
- In 1113 days, there are 6 complete days (3 days for A and 3 days for B) and 1 extra day (B works on the 1st day).
- Therefore, A works for 5 days and B works for 6 days.
5. Set Up the Equation for Total Work Done:
- Total work done = Work done by A + Work done by B
- Total Work=5×148+6×1b=1 (since they complete the whole work)
- This simplifies to:
548+6b=1
6. Solve for B's Work Rate:
- Rearranging gives:
6b=1−548
- Convert 1 to a fraction with a denominator of 48:
1=4848⟹6b=48−548=4348
- Cross-multiplying gives:
6×48=43b⟹288=43b⟹b=28843
7. Calculate the Time B Takes to Complete 4 Times the Work:
- If B can complete the work in 28843 days, then to complete 4 times the work:
Time for B to complete 4 times the work=4×28843=115243 days
Final Answer:
B alone can finish 4 times the same work in 115243 days, which is approximately 26.74 days.
- A can complete the work in 48 days.
- Therefore, the work done by A in one day = 148 of the work.
- Let the work done by B in one day be 1b.
- Since A and B work on alternate days, B works on the 1st, 3rd, 5th, etc., days, while A works on the 2nd, 4th, 6th, etc.
- The total time taken to complete the work is 1113 days, which can be converted to an improper fraction:
- 1113=343 days.
- In 1113 days, there are 6 complete days (3 days for A and 3 days for B) and 1 extra day (B works on the 1st day).
- Therefore, A works for 5 days and B works for 6 days.
- Total work done = Work done by A + Work done by B
- Total Work=5×148+6×1b=1 (since they complete the whole work)
- This simplifies to:
548+6b=1
- Rearranging gives:
6b=1−548
- Convert 1 to a fraction with a denominator of 48:
1=4848⟹6b=48−548=4348
- Cross-multiplying gives:
6×48=43b⟹288=43b⟹b=28843
- If B can complete the work in 28843 days, then to complete 4 times the work:
Time for B to complete 4 times the work=4×28843=115243 days
B alone can finish 4 times the same work in 115243 days, which is approximately 26.74 days.
Topper's Solved these Questions
Similar Questions
A and B can finish a work, working on alternate days, in 19 days, when A works on the first However, they can finish the work, working alternate days, in 1956 days, when B works on first day. How many days does A alone take finish the work? a. 1112 days b. 15 days c. 18 days d. 21 days
View SolutionBy working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View Solution
Knowledge Check
- Question 1 - Select One
A and B can finish a work in 15 days, B and C in 20 days, while C and A in 30 days, then A alone can finish the work in
A40 daysB24 daysC120 daysD13 days - Question 2 - Select One
A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :
A9B8C10D6 - Question 3 - Select One
A and B complete a work in 16 days, while A alone can finish that work in 24 days. In how many days, B alone can finish that work ?
A56 daysB48 daysC36 daysD64 days
By working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View SolutionA can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. C can alone do the work in
View SolutionA can finish a work in 18 days and B can do the same work in 15 days B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
(A) 5
(B) 5
(D) 8
(C) 6View SolutionA can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone?
View SolutionA can do a piece of work in 80 days. He works at it for 10 days and then B alone finishes the work in 42 days. The two together could complete the work in….
View Solution