A and B can finish a work, working on alternate days, in 19 days, when A works on the first However, they can finish the work, working alternate days, in 1956 days, when B works on first day. How many days does A alone take finish the work? a. 1112 days b. 15 days c. 18 days d. 21 days
To solve the problem, we need to find out how many days A alone takes to finish the work based on the information provided about A and B working on alternate days.
1. Understanding the Problem:
- Let A take x days to complete the work alone.
- Let B take y days to complete the work alone.
- When A starts first, they complete the work in 19 days.
- When B starts first, they complete the work in 1956 days.
2. Setting Up the Equations:
- When A starts first, A works for 10 days and B works for 9 days in 19 days.
- Therefore, the amount of work done can be expressed as:
10x+9y=1(Equation 1)
- When B starts first, B works for 10 days and A works for 9 days in 1956 days (which is 593 days).
- Therefore, the amount of work done can be expressed as:
9x+10y=1(Equation 2)
3. Multiplying the Equations:
- Multiply Equation 1 by 10:
10(10x+9y)=10⇒100x+90y=10(Equation 3)
- Multiply Equation 2 by 9:
9(9x+10y)=9⇒81x+90y=9(Equation 4)
4. Subtracting the Equations:
- Now, subtract Equation 4 from Equation 3:
(100x+90y)−(81x+90y)=10−9
100−81x=1⇒19x=1⇒x=19
5. Finding B's Work Rate:
- Substitute x=19 back into either Equation 1 or Equation 2 to find y.
- Using Equation 1:
1019+9y=1
9y=1−1019=919⇒y=19
6. Final Calculation:
- A takes 19 days to finish the work alone.
Conclusion:
A alone takes 19 days to finish the work.
- Let A take x days to complete the work alone.
- Let B take y days to complete the work alone.
- When A starts first, they complete the work in 19 days.
- When B starts first, they complete the work in 1956 days.
- When A starts first, A works for 10 days and B works for 9 days in 19 days.
- Therefore, the amount of work done can be expressed as:
10x+9y=1(Equation 1)
- Therefore, the amount of work done can be expressed as:
9x+10y=1(Equation 2)
- Multiply Equation 1 by 10:
10(10x+9y)=10⇒100x+90y=10(Equation 3)
9(9x+10y)=9⇒81x+90y=9(Equation 4)
- Now, subtract Equation 4 from Equation 3:
(100x+90y)−(81x+90y)=10−9
100−81x=1⇒19x=1⇒x=19
- Substitute x=19 back into either Equation 1 or Equation 2 to find y.
- Using Equation 1:
1019+9y=1
9y=1−1019=919⇒y=19
- A takes 19 days to finish the work alone.
A alone takes 19 days to finish the work.
Topper's Solved these Questions
Similar Questions
By working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View SolutionBy working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View Solution
Knowledge Check
A and B can finish a work in 15 days, B and C in 20 days, while C and A in 30 days, then A alone can finish the work in
A40 daysB24 daysC120 daysD13 daysTo do a certain work, A and B work on alternate days, with B beginning the work on the first day. A can finish the work alone in 48 days. If the work gets completed in 1113 days, then B alone can finish 4 times the same work in:
A24 daysB32 daysC27 daysD30 days
A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. In how many days can A alone finish the work?
View SolutionA can do a work in 12 days. B works60% more fast than A then in how many days B alone could finish this work ?
View SolutionA can do a piece of work in 15 days, which B can do in 10 days. B worked at it for 8 days. A can finish the remaining work in 2 days b. 3 days c. 5 days d. 10 days
View SolutionA is twice as good a workman as B and together they finish a piece of work in 18 days. In how many days will A alone finish the work?
View SolutionA is twice as good a work man as B together they finish a piece of work in 18 days . In how many days will A alone finish the work ?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 20 days. In how many days will A alone finish the work?
View Solution