Doubtnut Promotions Sticky

A and B can finish a work, working on alternate days, in 19 days, when A works on the first However, they can finish the work, working alternate days, in 1956 days, when B works on first day. How many days does A alone take finish the work? a. 1112 days b. 15 days c. 18 days d. 21 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we need to find out how many days A alone takes to finish the work based on the information provided about A and B working on alternate days.

1. Understanding the Problem:
- Let A take x days to complete the work alone.
- Let B take y days to complete the work alone.
- When A starts first, they complete the work in 19 days.
- When B starts first, they complete the work in 1956 days.

2. Setting Up the Equations:
- When A starts first, A works for 10 days and B works for 9 days in 19 days.
- Therefore, the amount of work done can be expressed as:
10x+9y=1(Equation 1)

- When B starts first, B works for 10 days and A works for 9 days in 1956 days (which is 593 days).
- Therefore, the amount of work done can be expressed as:
9x+10y=1(Equation 2)

3. Multiplying the Equations:
- Multiply Equation 1 by 10:
10(10x+9y)=10100x+90y=10(Equation 3)

- Multiply Equation 2 by 9:
9(9x+10y)=981x+90y=9(Equation 4)

4. Subtracting the Equations:
- Now, subtract Equation 4 from Equation 3:
(100x+90y)(81x+90y)=109
10081x=119x=1x=19

5. Finding B's Work Rate:
- Substitute x=19 back into either Equation 1 or Equation 2 to find y.
- Using Equation 1:
1019+9y=1
9y=11019=919y=19

6. Final Calculation:
- A takes 19 days to finish the work alone.

Conclusion:
A alone takes 19 days to finish the work.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can finish a work in 15 days, B and C in 20 days, while C and A in 30 days, then A alone can finish the work in

    A40 days
    B24 days
    C120 days
    D13 days
  • Question 2 - Select One

    To do a certain work, A and B work on alternate days, with B beginning the work on the first day. A can finish the work alone in 48 days. If the work gets completed in 1113 days, then B alone can finish 4 times the same work in:

    A24 days
    B32 days
    C27 days
    D30 days