Doubtnut Promotions Sticky

To do a certain work, the ratio of the efficiencies of X and Y is 5:4. Working together, they can complete the same work in 10 days. Y alone starts the work and leaves after 5 days. The remaining work will be completed by X alone in :

A

14 days

B

12 days

C

15 days

D

10 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the efficiencies of X and Y
The ratio of the efficiencies of X and Y is given as 5:4. This means:
- Efficiency of X = 5 units of work per day
- Efficiency of Y = 4 units of work per day

Step 2: Calculate the total work
When X and Y work together, they complete the work in 10 days.
- The combined efficiency of X and Y = 5 + 4 = 9 units of work per day.
- Therefore, the total work = Combined efficiency × Total days = 9 units/day × 10 days = 90 units of work.

Step 3: Calculate the work done by Y in 5 days
Y starts the work and works for 5 days.
- Work done by Y in 5 days = Efficiency of Y × Number of days = 4 units/day × 5 days = 20 units of work.

Step 4: Calculate the remaining work
Now, we need to find out how much work is left after Y has worked for 5 days.
- Remaining work = Total work - Work done by Y = 90 units - 20 units = 70 units of work.

Step 5: Calculate the time taken by X to complete the remaining work
Now, X will complete the remaining work alone.
- Efficiency of X = 5 units of work per day.
- Time taken by X to complete the remaining work = Remaining work / Efficiency of X = 70 units / 5 units/day = 14 days.

Final Answer
The remaining work will be completed by X alone in 14 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    To do a certain work the ratio of the efficincies of A, B and C is 7:5:6. Working together they can complete the same work in 35 days. B and C work together for 21 days. The remaining work will be completed by A alone in:

    A60 days
    B57 days
    C54 days
    D50 days
  • Question 2 - Select One

    The ratio of the efficiencies of A, B and C to do a certain work is 7:3:5. Working together, they can complete the work in 21 days. A and C worked together for 5 days. The remaining work will be completed by B alone in :

    A54 days
    B45 days
    C60 days
    D85 days
  • Question 3 - Select One

    The ratio of the efficiencies of A, B and C is 3: 5:1. Working together, they can complete a piece of work in 5 days. A and B work together for 3 days. The remaining work will be completed by C alone in?

    A18 days
    B24 days
    C21 days
    D15 days