Doubtnut Promotions Sticky

(A + B) can do a piece of work in 10 days. A works 212 days and B works for 812 days, then half of the work has been completed. In how many days will B do this work alone ?

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:24 days


To solve the problem step by step, we will use the information given in the question.

Step 1: Determine the total work done by A and B together.

Given that A + B can complete the work in 10 days, we can express the total work (W) in terms of their combined work rate.

Work Rate of (A + B)=110 (work per day)

Thus, the total work can be calculated as:

W=Work Rate×Time=110×10=1 (whole work)

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    (A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?

    A18,15.,20
    B30,20,10
    C10,15,25
    D15,10,25
  • Question 2 - Select One

    A can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?

    A12
    B10
    C9.6
    D9
  • Question 3 - Select One

    A can do a piece of work in 30 days. He worked for 6 days and B finished the remaining work in 48 days. B alone can do the whole work in how many days?

    A60
    B55
    C75
    D70