(A + B) can do a piece of work in 10 days. A works 212 days and B works for 812 days, then half of the work has been completed. In how many days will B do this work alone ?
The correct Answer is:24 days
To solve the problem step by step, we will use the information given in the question.
Step 1: Determine the total work done by A and B together.
Given that A + B can complete the work in 10 days, we can express the total work (W) in terms of their combined work rate.
Work Rate of (A + B)=110 (work per day)
Thus, the total work can be calculated as:
W=Work Rate×Time=110×10=1 (whole work)
Topper's Solved these Questions
Similar Questions
(A + B) can do a piece of work in 14 days. A works 312 days and B works for 1112 days, then half of the work has been completed. In how many days will B do this work alone ?
View Solution(A + B) can do a piece of work in 5 days. If A works with twice of his efficiency and B works with 13 of his efficiency, then work will be completed in 3 days. In how many days will A do this work alone ?
View Solution
Knowledge Check
- Question 1 - Select One
(A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?
A18,15.,20B30,20,10C10,15,25D15,10,25 - Question 2 - Select One
A can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?
A12B10C9.6D9 - Question 3 - Select One
A can do a piece of work in 30 days. He worked for 6 days and B finished the remaining work in 48 days. B alone can do the whole work in how many days?
A60B55C75D70
(A + B) can do a piece of work in 12 days. (B + C) can do same work in 16 days. A work for 5 days, B works for 7 days and C completed the remaining work in 13 days. In how many days will A, B and C do this work alone ?
View Solution(A + B) can do a piece of work in 5 days. If A works with twice of his efficiency and B works with half of his efficiency, then work will be completed in 4 days. In how many days will A and B do this work alone ?
View SolutionA and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days. A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?
View SolutionA can do a piece of work in 10 days and B can do same work in 15 days. Both A and B start the work and after 3 days B left. In how many days will A do the remaining work?
View SolutionA can do a piece of work in 20 days. He worked for 5 days and B finished the remaining work in 42 days. B alone can do the whole work in how many days?
View Solution