Doubtnut Promotions Sticky

A contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?

A

15

B

20

C

25

D

30

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:B

|
Answer

Step by step video, text & image solution for A contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A contractor undertakes to make a mall in 60 days and he
    employs 30 men. After 30 days it is found that only one-
    third of the work is completed. How many extre men should
    he employ so that the work is completed on time?

    A20 men
    B25 men
    C30 men
    D40 men
  • Question 2 - Select One

    A contract is to be completed in 75 days and 187 men are to work 15 hours per day. After 65 days, 3/5 of the work is completed. How many additional men may be employed, so that the work may be completed in time each man now working 17 hours per day?

    A495
    B514
    C528
    D532
  • Question 3 - Select One

    A contract is to be completed in 92 days and 234 men set to work , each working 16h a day. After 66 days , 4/7 of the work is completed. How many additional men many be employed , so that the work may be completed in time , each man now working 18h a day ?

    A162
    B234
    C262
    D81