Doubtnut Promotions Sticky

A alone can do a plece of work in 20 days and B alone in 30 days. They begin to work together. They will finish half of the work in :

A

8 days

B

9 days

C

12 days

D

6 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will determine how long it takes for A and B to finish half of the work together.

Step 1: Determine the work done by A and B in one day.
- A can complete the work in 20 days, so the work done by A in one day is:
Work done by A in one day=120
- B can complete the work in 30 days, so the work done by B in one day is:
Work done by B in one day=130

Step 2: Calculate the total work done by A and B together in one day.
- To find the total work done by A and B together in one day, we add their individual contributions:
Total work done in one day=120+130
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 20 and 30 is 60.
120=360and130=260
- Now we can add them:
Total work done in one day=360+260=560=112

Step 3: Calculate the time taken to complete the entire work.
- Since A and B together can complete 112 of the work in one day, the time taken to complete the entire work is:
Time to complete the work=1112=12 days

Step 4: Calculate the time taken to complete half of the work.
- To find the time taken to complete half of the work, we simply take half of the total time:
Time to complete half of the work=122=6 days

Final Answer:
A and B together will finish half of the work in 6 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a piece of work in 120 days and B can do it in 150 days. They work together for 20 days. Then B leaves and A alone continues the work. 12 days after that C joins A and the work is completed in 48 days more. In how many days can C do it if he works alone?

    A230 days
    B225 days
    C240 days
    D220 days
  • Question 2 - Select One

    A alone can finish a piece of work in 10 days which B alone can do in 15 days. If they work together and finish it, then out of total wages of Rs 3000, A will get

    ARs 1200
    BRs 1500
    CRs 1800
    DRs 20000
  • Question 3 - Select One

    A can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave the work. Then Calone finIshes the remaining work in 10 days. In how many days will finish the full work?

    A25 days
    B30 days
    C24 days
    D20 days