If 28 men complete 78 of a plece of work in a week, then the number of men, who must be engaged to get the remaining work completed in another week, is
5
6
4
3
The correct Answer is:C
To solve the problem step by step, let's break it down:
Step 1: Determine the amount of work done by 28 men in a week.
Given that 28 men complete 78 of the work in one week, we can calculate how much work one man can do in a week.
Calculation:
- Work done by 28 men in a week = 78
- Work done by 1 man in a week = 78÷28=78×128=7224=132
Step 2: Calculate the remaining work.
The total work is considered as 1 (or 100%). Since 78 of the work is done, the remaining work is:
Calculation:
- Remaining work = Total work - Work done = 1−78=18
Step 3: Determine how many men are needed to complete the remaining work in one week.
Now we know that one man can complete 132 of the work in a week. We need to find out how many men are required to complete 18 of the work in one week.
Calculation:
- Let x be the number of men needed.
- Work done by x men in one week = x×132
- We want this to equal 18:
x×132=18
Step 4: Solve for x.
To find x, we can rearrange the equation:
Calculation:
x=18÷132=18×321=328=4
Conclusion:
Thus, the number of men required to complete the remaining work in one week is 4.
---
Given that 28 men complete 78 of the work in one week, we can calculate how much work one man can do in a week.
- Work done by 28 men in a week = 78
- Work done by 1 man in a week = 78÷28=78×128=7224=132
The total work is considered as 1 (or 100%). Since 78 of the work is done, the remaining work is:
- Remaining work = Total work - Work done = 1−78=18
Now we know that one man can complete 132 of the work in a week. We need to find out how many men are required to complete 18 of the work in one week.
- Let x be the number of men needed.
- Work done by x men in one week = x×132
- We want this to equal 18:
x×132=18
To find x, we can rearrange the equation:
x=18÷132=18×321=328=4
Thus, the number of men required to complete the remaining work in one week is 4.
Topper's Solved these Questions
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TEST YOURSELF25videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-V19videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI74videos
TIME AND DISTANCE
- BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF25videos
TRIGONOMETRY
Similar Questions
Knowledge Check
- Question 1 - Select One
7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work
A28B21C14D7 - Question 2 - Select One
20 men or 24 women can complete a piece of work in 20 days. If 30 men and 112 women under take to complete the work, the work will be completed in:
A10 daysB12 daysC15 daysD16 days - Question 3 - Select One
Working efficiencies of P and Q for completing a piece of work are in the ratio 3:4. The number of days to be taken by them to complete the work will be in the ratio
A3:2B2:3C3:4D4:3
24 men can complete a piece of work in 16 days and 18 women can complete the same work in 32 days. 12 men and 6 women work together for 16 days. If the remaining work was to be completed in 2 days, how many additional men would be required besisdes 12 men and 6 women ?
View Solution20 men or 24 women can complete a piece of work in 20 days. If 30 men and 112 women under take to complete the work, the work will be completed in:
View Solution12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men are engaged in the same work ?
View Solution24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
View SolutionTwenty two men can complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
View Solution