Doubtnut Promotions Sticky

If 28 men complete 78 of a plece of work in a week, then the number of men, who must be engaged to get the remaining work completed in another week, is

A

5

B

6

C

4

D

3

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, let's break it down:

Step 1: Determine the amount of work done by 28 men in a week.
Given that 28 men complete 78 of the work in one week, we can calculate how much work one man can do in a week.

Calculation:
- Work done by 28 men in a week = 78
- Work done by 1 man in a week = 78÷28=78×128=7224=132

Step 2: Calculate the remaining work.
The total work is considered as 1 (or 100%). Since 78 of the work is done, the remaining work is:

Calculation:
- Remaining work = Total work - Work done = 178=18

Step 3: Determine how many men are needed to complete the remaining work in one week.
Now we know that one man can complete 132 of the work in a week. We need to find out how many men are required to complete 18 of the work in one week.

Calculation:
- Let x be the number of men needed.
- Work done by x men in one week = x×132
- We want this to equal 18:

x×132=18

Step 4: Solve for x.
To find x, we can rearrange the equation:

Calculation:
x=18÷132=18×321=328=4

Conclusion:
Thus, the number of men required to complete the remaining work in one week is 4.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work

    A28
    B21
    C14
    D7
  • Question 2 - Select One

    20 men or 24 women can complete a piece of work in 20 days. If 30 men and 112 women under take to complete the work, the work will be completed in:

    A10 days
    B12 days
    C15 days
    D16 days
  • Question 3 - Select One

    Working efficiencies of P and Q for completing a piece of work are in the ratio 3:4. The number of days to be taken by them to complete the work will be in the ratio

    A3:2
    B2:3
    C3:4
    D4:3