Doubtnut Promotions Sticky

A can do a piece of work in 40 days. He works on it for 5 days and then B completes it in 21 days. How long will A and B together take to complete the work?

A

10 days

B

15 days

C

20 days

D

25 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, let's break it down:

Step 1: Determine A's Work Rate
A can complete the work in 40 days. Therefore, A's work rate (efficiency) is:
Work rate of A=1 work40 days=140 work/day

Step 2: Calculate Work Done by A in 5 Days
In 5 days, A will complete:
Work done by A in 5 days=5×140=540=18 of the work

Step 3: Calculate Remaining Work
The total work is considered as 1 unit. After A works for 5 days, the remaining work is:
Remaining work=118=78

Step 4: Determine B's Work Rate
Let B's work rate be b. Since A and B together complete the remaining work in 21 days, we can express this as:
Work done by B in 21 days=21b
Since B completes the remaining work of 78:
21b=78

Step 5: Solve for B's Work Rate
To find B's work rate, rearrange the equation:
b=78×21=7168=124 work/day

Step 6: Calculate A and B's Combined Work Rate
Now we can find the combined work rate of A and B:
Combined work rate=140+124
To add these fractions, find a common denominator (which is 120):
140=3120,124=5120
Thus,
Combined work rate=3120+5120=8120=115 work/day

Step 7: Calculate Time Taken by A and B Together
To find out how long A and B together will take to complete the entire work:
Time=Total WorkCombined Work Rate=1115=15 days

Final Answer
A and B together will take 15 days to complete the work.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    X can do a piece of work in 40 days. He works it for 8 days and then Y finished it in 16 days How long will they together take to complete the work?

    A1313 days
    B15 days
    C20 days
    D56 days
  • Question 2 - Select One

    A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

    A38
    B51
    C46
    D62
  • Question 3 - Select One

    A alone can complete a piece of work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work ?

    A18 days
    B24 days
    C16 days
    D20 days