A can do a piece of work in 40 days. He works on it for 5 days and then B completes it in 21 days. How long will A and B together take to complete the work?
10 days
15 days
20 days
25 days
The correct Answer is:B
To solve the problem step by step, let's break it down:
Step 1: Determine A's Work Rate
A can complete the work in 40 days. Therefore, A's work rate (efficiency) is:
Work rate of A=1 work40 days=140 work/day
Step 2: Calculate Work Done by A in 5 Days
In 5 days, A will complete:
Work done by A in 5 days=5×140=540=18 of the work
Step 3: Calculate Remaining Work
The total work is considered as 1 unit. After A works for 5 days, the remaining work is:
Remaining work=1−18=78
Step 4: Determine B's Work Rate
Let B's work rate be b. Since A and B together complete the remaining work in 21 days, we can express this as:
Work done by B in 21 days=21b
Since B completes the remaining work of 78:
21b=78
Step 5: Solve for B's Work Rate
To find B's work rate, rearrange the equation:
b=78×21=7168=124 work/day
Step 6: Calculate A and B's Combined Work Rate
Now we can find the combined work rate of A and B:
Combined work rate=140+124
To add these fractions, find a common denominator (which is 120):
140=3120,124=5120
Thus,
Combined work rate=3120+5120=8120=115 work/day
Step 7: Calculate Time Taken by A and B Together
To find out how long A and B together will take to complete the entire work:
Time=Total WorkCombined Work Rate=1115=15 days
Final Answer
A and B together will take 15 days to complete the work.
---
A can complete the work in 40 days. Therefore, A's work rate (efficiency) is:
Work rate of A=1 work40 days=140 work/day
In 5 days, A will complete:
Work done by A in 5 days=5×140=540=18 of the work
The total work is considered as 1 unit. After A works for 5 days, the remaining work is:
Remaining work=1−18=78
Let B's work rate be b. Since A and B together complete the remaining work in 21 days, we can express this as:
Work done by B in 21 days=21b
Since B completes the remaining work of 78:
21b=78
To find B's work rate, rearrange the equation:
b=78×21=7168=124 work/day
Now we can find the combined work rate of A and B:
Combined work rate=140+124
To add these fractions, find a common denominator (which is 120):
140=3120,124=5120
Thus,
Combined work rate=3120+5120=8120=115 work/day
To find out how long A and B together will take to complete the entire work:
Time=Total WorkCombined Work Rate=1115=15 days
A and B together will take 15 days to complete the work.
Topper's Solved these Questions
Similar Questions
A alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work?
View SolutionA can do a piece of work in 80 days. A works for 10 days, then B complete the remaining work in 42 days. In how many days will (A + B) do this work together
View Solution
Knowledge Check
- Question 1 - Select One
X can do a piece of work in 40 days. He works it for 8 days and then Y finished it in 16 days How long will they together take to complete the work?
A1313 daysB15 daysC20 daysD56 days - Question 2 - Select One
A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
A38B51C46D62 - Question 3 - Select One
A alone can complete a piece of work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work ?
A18 daysB24 daysC16 daysD20 days
A and B working together can do a piece of work in 12 days and A alone can caomplete the work in 18 days. How long will B alone take to complete the job?
View SolutionA and B together can do a piece of work in 12 days and A alone can complete the work in 18 days. How long will B alone take to complete the job ?
View SolutionA and B together can do a piece of work in 12 days and A alone can complete the work in 18 days. How long will B alone take to complete the job ?
View SolutionA man, a woman and a boy can together complete a piece of work In 3 days. If a man alone can do it in 6 days and a boy alone in 18 days, how long will a woman alone take to complete the work?
View SolutionAbhishek can do a piece of work in 40 days. He alone worked at it for 8 days and then Bacchhan completed alone the rest work in 24 days. In how many days they will complete the whole work, working together ?
View Solution