Doubtnut Promotions Sticky

A and B can complete a piece of work in 45 and 40 days respectively. Both started to work together, but after some days A left and B alone completed the rest work in 23 days. For how many days did A work?

A

12 days

B

10 days

C

8 days

D

9 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the total work
A can complete the work in 45 days, and B can complete it in 40 days. We can find the total work in terms of work units. The least common multiple (LCM) of 45 and 40 will give us the total work.

- LCM of 45 and 40 = 360 units of work.

Step 2: Calculate the work efficiency of A and B
Next, we calculate the work efficiency of A and B.

- A's efficiency = Total work / Time taken by A = 360 / 45 = 8 units/day.
- B's efficiency = Total work / Time taken by B = 360 / 40 = 9 units/day.

Step 3: Calculate the work done by B alone
B worked alone for 23 days. We can calculate how much work B completed during this time.

- Work done by B in 23 days = B's efficiency * Number of days = 9 units/day * 23 days = 207 units.

Step 4: Calculate the remaining work
Now, we need to find out how much work is left after B has completed his part.

- Remaining work = Total work - Work done by B = 360 - 207 = 153 units.

Step 5: Calculate the combined efficiency of A and B
When A and B work together, their combined efficiency is:

- Combined efficiency = A's efficiency + B's efficiency = 8 units/day + 9 units/day = 17 units/day.

Step 6: Calculate the time taken by A and B together to finish the remaining work
Now we can find out how many days A and B worked together to complete the remaining work.

- Time taken to complete remaining work = Remaining work / Combined efficiency = 153 units / 17 units/day = 9 days.

Step 7: Conclusion
Since A and B worked together for 9 days, we conclude that A worked for 9 days before leaving the work to B.

Final Answer:
A worked for 9 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave ?

    A1425 days
    B9days
    C8days
    D759 days
  • Question 2 - Select One

    A and B can do a piece of work in 20 and 25 days respectively. They began to work together but A leaves after sometime and B completed remaining work in 17 days. After how many days did A leave?

    A1425 days
    B9 days
    C8 days
    D359 days
  • Question 3 - Select One

    A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?

    A14
    B12
    C18
    D10