Doubtnut Promotions Sticky

A can do a piece of work in 120 days and B can do it in 150 days. They work together for 20 days. Then B leaves and A alone continues the work. 12 days after that C joins A and the work is completed in 48 days more. In how many days can C do it if he works alone?

A

230 days

B

225 days

C

240 days

D

220 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will first calculate the work done by A and B together, then find out how much work is left for A and C to complete.

Step 1: Calculate the work done by A and B together.

1. Find the work done by A in one day:
- A can complete the work in 120 days.
- Work done by A in one day = 1120 of the work.

2. Find the work done by B in one day:
- B can complete the work in 150 days.
- Work done by B in one day = 1150 of the work.

3. Find the combined work done by A and B in one day:
- Combined work per day = 1120+1150
- To add these fractions, we need a common denominator. The LCM of 120 and 150 is 600.
- Convert the fractions:
- 1120=5600
- 1150=4600
- Combined work per day = 5600+4600=9600=3200

4. Calculate the work done in 20 days:
- Work done in 20 days = 20×3200=60200=310

Step 2: Calculate the remaining work after A and B work together for 20 days.

1. Total work = 1 (whole work)
2. Remaining work = Total work - Work done in 20 days
- Remaining work = 1310=710

Step 3: Calculate the work done by A alone for 12 days.

1. Work done by A in 12 days:
- Work done by A in 12 days = 12×1120=12120=110

2. Remaining work after A works alone for 12 days:
- Remaining work = 710110=610=35

Step 4: Calculate the work done by A and C together for 48 days.

1. Let C's work rate be 1C (C can do the work in C days).
2. Combined work rate of A and C:
- Work done by A and C together = 1120+1C

3. Work done in 48 days:
- Work done in 48 days = 48(1120+1C)=35

Step 5: Set up the equation and solve for C.

1. Set up the equation:
- 48(1120+1C)=35

2. Multiply both sides by 120C to eliminate the fractions:
- 48C+48×120=3×120C5
- 48C+5760=72C

3. Rearranging gives:
- 5760=72C48C
- 5760=24C
- C=576024=240

Conclusion:
C can complete the work alone in 240 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a piece of work in 10 days and B can do it in 12 days. They work together for 3 days. Then B leaves and A alone continues. 2 days after that C joins and the work is completed in 2 days more. In how many days can C do it, if he works alone ?

    A40 days
    B50 days
    C40 days
    D60 days
  • Question 2 - Select One

    A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?

    A7days
    B712 days
    C8 days
    D812days
  • Question 3 - Select One

    A can do a work in 20 days. A and B can do it in 12 days together. In how many days B can do it alone?

    A25
    B20
    C30
    D15