Doubtnut Promotions Sticky

If A can complete a project in 3 days, B can complete the same project in 4 days while C can complete it in 5 days. All of them stated the project together but after 3 days C left, after 4 days B left and after 5 days A left, then how many projects they have finished in 5 days?

A

2

B

1

C

3

D

4

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we first need to determine the work done by each person (A, B, and C) in a day and then calculate how much work they complete together over the specified time.

Step 1: Determine the work rate of A, B, and C
- A can complete the project in 3 days, so A's work rate is:
Work rate of A=1 project3 days=13 projects per day
- B can complete the project in 4 days, so B's work rate is:
Work rate of B=1 project4 days=14 projects per day
- C can complete the project in 5 days, so C's work rate is:
Work rate of C=1 project5 days=15 projects per day

Step 2: Find the combined work rate of A, B, and C
To find the total work rate when all three work together, we add their individual work rates:
Combined work rate=13+14+15
To add these fractions, we need a common denominator. The least common multiple (LCM) of 3, 4, and 5 is 60. Thus, we convert each fraction:
13=2060,14=1560,15=1260
Now we can add them:
Combined work rate=2060+1560+1260=4760 projects per day

Step 3: Calculate the work done in the first 3 days
In the first 3 days, all three work together:
Work done in 3 days=3×4760=14160 projects

Step 4: Calculate the work done by B and A after C leaves
After 3 days, C leaves. Now A and B continue working together for the next day (Day 4):
Work done by A and B in 1 day=13+14=2060+1560=3560 projects
So, after Day 4, the total work done is:
Total work after 4 days=14160+3560=17660 projects

Step 5: Calculate the work done by A alone on Day 5
On Day 5, A works alone:
Work done by A in 1 day=13=2060 projects
Now, adding this to the total work done:
Total work after 5 days=17660+2060=19660 projects

Step 6: Calculate the number of complete projects finished
To find out how many complete projects they finished, we divide the total work done by the work required for one project:
Number of projects completed=196603.27
Since we can only count complete projects, they finished 3 complete projects.

Final Answer
Thus, the total number of projects they have finished in 5 days is 3.

---

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B complete a piece of work 12 days B and C can complete in 24,days. A and C can complete it in 16 days. In how many days can B alone complete it?

    A16
    B32
    C12
    D20
  • Question 2 - Select One

    A can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?

    A6
    B214
    C812
    D9
  • Question 3 - Select One

    A and B together can complete a work in 30 days. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?

    A45
    B90
    C60
    D120