If A can complete a project in 3 days, B can complete the same project in 4 days while C can complete it in 5 days. All of them stated the project together but after 3 days C left, after 4 days B left and after 5 days A left, then how many projects they have finished in 5 days?
2
1
3
4
The correct Answer is:C
Step by step video, text & image solution for If A can complete a project in 3 days, B can complete the same project in 4 days while C can complete it in 5 days. All of them stated the project together but after 3 days C left, after 4 days B left and after 5 days A left, then how many projects they have finished in 5 days? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
Similar Questions
A can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?
View Solution15 men can complete a work in 12 days they start the work together . In how many days the total work will be finished when.
After 4 days 5 men left the work .View Solution
Knowledge Check
- Question 1 - Select One
A and B complete a piece of work 12 days B and C can complete in 24,days. A and C can complete it in 16 days. In how many days can B alone complete it?
A16B32C12D20 - Question 2 - Select One
A can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?
A6B214C812D9 - Question 3 - Select One
A and B together can complete a work in 30 days. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
A45B90C60D120
A and B together can complete a work in 30 days. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
View SolutionA and B together can complete a work in 3 days. They started together but after 2 days, B left the work. If the work is completed after 2 more days, Balone could do the work in how many days?
View SolutionA and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in
View SolutionA and B can complete a job in 24 days working together. A alone can complete it in 32 days. Both of them worked together for 8 days and then A left. The number of days B will take to complete the remaining job is
View SolutionA and B can complete a work in 8 days B & C can complete that work in 12 days and C and A completes that work in 8 days. Accordingly, in how many days all the three can complete that work ?
View Solution