24 men working 8 hours a day can finish a work in 10 days. Working at the rate of 10 hours a day, the number of men required to finish the same work in 6 days is:
a. 30
b. 32
c. 34
d. 36
The correct Answer is:B
To solve the problem, we will first calculate the total amount of work done in the first scenario and then determine how many men are needed in the second scenario to complete the same work in a different timeframe.
Step 1: Calculate the total work done in the first scenario.
The total work can be calculated using the formula:
Total Work=Number of Men×Hours per Day×Days
From the problem:
- Number of Men = 24
- Hours per Day = 8
- Days = 10
Now, substituting the values into the formula:
Total Work=24×8×10
Calculating this:
Total Work=1920 man-hours
Step 2: Set up the equation for the second scenario.
In the second scenario, we need to find out how many men (let's call this x) are required to complete the same amount of work (1920 man-hours) when they work:
- Hours per Day = 10
- Days = 6
Using the same formula for total work, we have:
Total Work=x×10×6
Step 3: Equate the total work from both scenarios.
Since both scenarios complete the same amount of work:
1920=x×10×6
Step 4: Solve for x.
First, calculate 10×6:
10×6=60
Now, we can rewrite the equation:
1920=x×60
To find x, divide both sides by 60:
x=192060
Calculating this gives:
x=32
Conclusion:
The number of men required to finish the same work in 6 days, working 10 hours a day, is 32 men.
---
Total Work=Number of Men×Hours per Day×Days
- Number of Men = 24
- Hours per Day = 8
- Days = 10
Total Work=24×8×10
Total Work=1920 man-hours
- Hours per Day = 10
- Days = 6
Total Work=x×10×6
1920=x×10×6
10×6=60
1920=x×60
x=192060
x=32
Topper's Solved these Questions
- DEFINITE INTEGRATION BOOK - PUNEET DOGRACHAPTER - DEFINITE INTEGRATION EXERCISE - PREVIOUS YEAR QUESTIONS
65 Videos
- CONIC SECTIONBOOK - PUNEET DOGRACHAPTER - CONIC SECTIONEXERCISE - PREV YEAR QUESTIONS
37 Videos
- DETERMINANTS BOOK - PUNEET DOGRACHAPTER - DETERMINANTS EXERCISE - PREV YEAR QUESTIONS
55 Videos
Similar Questions
12 men working 8 hours per day complete a piece of work in 10 days. To complete the same work in 8 days, working 15 hours a day, the number of men required is a. 4 b. 5 c. 6 d. 8
View Solution2 men each working 5 hour per day can finish a job in 12 days. How long will 4 men each working 2 hours per day take to finish the same job?
View Solution
Knowledge Check
Working 7 hours in a day, 4 men can do a piece of work in 8 days. Working 8 hours in a day, the required number of men to perform the same work in 4 days will be
A1. 8B2. 4C3. 7D4. 9If 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.
A6 hoursB(6)1/2 hoursC7 hoursD9 hoursIf 9 men working 712 hours a day can finish a piece of work in 20 days, then how many days will be taken by 12 men, working 6 hours a day to finish the work? It is being given that 2 men of latter type work as much as 3 men of the former type. 11 b. 13 c. 912 d. 1212
A12.5B13C9.5D11
4 men, each working 6 hours per day can build a wall in 9 days. How long will 6 men, each working 3 hours per day take to finish the same work?
View Solution8 men can finish a work in 40 days .If 2 more men would join them ,then how much days will required to finish the work ?
View SolutionIf 60 boys can finish a work in 15 days by working 8 hours a day, then how many hours a day should 72 boys work to finish that work within 20 days?
View SolutionIf 35 men can finish a piece of work in 8 days, then the number of men who can do the same work in 10 days is :
View Solution10 men working 8 hours day can do a work in 30 days. In how many days will 12 men working 4 hours a day take do the same work?
View Solution