24 men working 8 hours a day can finish a work in 10 days. Working at the rate of 10 hours a day, the number of men required to finish the same work in 6 days is:

A

a. 30

B

b. 32

C

c. 34

D

d. 36

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we will first calculate the total amount of work done in the first scenario and then determine how many men are needed in the second scenario to complete the same work in a different timeframe.

Step 1: Calculate the total work done in the first scenario.

The total work can be calculated using the formula:
Total Work=Number of Men×Hours per Day×Days

From the problem:
- Number of Men = 24
- Hours per Day = 8
- Days = 10

Now, substituting the values into the formula:
Total Work=24×8×10

Calculating this:
Total Work=1920 man-hours

Step 2: Set up the equation for the second scenario.

In the second scenario, we need to find out how many men (let's call this x) are required to complete the same amount of work (1920 man-hours) when they work:
- Hours per Day = 10
- Days = 6

Using the same formula for total work, we have:
Total Work=x×10×6

Step 3: Equate the total work from both scenarios.

Since both scenarios complete the same amount of work:
1920=x×10×6

Step 4: Solve for x.

First, calculate 10×6:
10×6=60

Now, we can rewrite the equation:
1920=x×60

To find x, divide both sides by 60:
x=192060

Calculating this gives:
x=32

Conclusion:

The number of men required to finish the same work in 6 days, working 10 hours a day, is 32 men.

---

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Working 7 hours in a day, 4 men can do a piece of work in 8 days. Working 8 hours in a day, the required number of men to perform the same work in 4 days will be

    A1. 8
    B2. 4
    C3. 7
    D4. 9
  • If 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.

    A6 hours
    B(6)1/2 hours
    C7 hours
    D9 hours
  • If 9 men working 712 hours a day can finish a piece of work in 20 days, then how many days will be taken by 12 men, working 6 hours a day to finish the work? It is being given that 2 men of latter type work as much as 3 men of the former type. 11 b. 13 c. 912 d. 1212

    A12.5
    B13
    C9.5
    D11