50 men can complete a work in 28 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?
60
30
40
50
The correct Answer is:D
Step by step video, text & image solution for 50 men can complete a work in 28 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Similar Questions
15 men can complete a work in 12 days they start the work together . In how many days the total work will be finished when.
After 4 days 5 men left the work .View SolutionA can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?
View Solution
Knowledge Check
- Question 1 - Select One
40 men can complete a work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in
A5623 daysB5313 daysC52 daysD50 days - Question 2 - Select One
40 men can complete a work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in
A5623 daysB5313 daysC52 daysD50 days - Question 3 - Select One
50 people can complete a work in 50 days. They started the work together but at the end of every 10th day 5 people join the work. In how much time the work would be completed?
A1. 5217B2. 4727C3. 4267D4. 4257
25 men can complete a work in 10 days. 20 boys can complete this work in 50 days. 5 men start the work and aftr 10 days 10 boys joined them and remaining work is completed in 20 days. How many boys are joined ?
View Solution24 men can complete a piece of work in 16 days and 18 women can complete the same work in 32 days. 12 men and 6 women work together for 16 days. If the remaining work was to be completed in 2 days, how many additional men would be required besisdes 12 men and 6 women ?
View Solution15 men can complete a work in 210 days. They started the work but at the end of 10 days, 15 additional men, with double efficiency, were in- ducted. How many days in all did they take to finish the work ?
View SolutionA and B together can complete a work in 3 days. They started together but after 2 days, B left the work. If the work is completed after 2 more days, Balone could do the work in how many days?
View SolutionTwelve men can complete a work in 8 days. Three days after they started the work, 3 more men joined them. In how many days will all of them together complete the remaining work ?
View Solution