7 men can complete a work in 12 day. They started the work and after 5 days, two men left. In how many days will the work be completed by the remaining men? a.5 b.6 c.7 d.8 e. none of these
Step by step video & image solution for 7 men can complete a work in 12 day. They started the work and after 5 days, two men left. In how many days will the work be completed by the remaining men? a. 5 b. 6 c. 7 d. 8 e. none of these by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
Similar Questions
7 men can complete a work in 12 day. They started the work and after 5 days, two men left. In how many days will the work be completed by the remaining men? a.5 b.6 c.7 d.8 e. none of these
View Solution45 men can complete a work in 16 days. Six days after they started working, 30 more men joined them. How many days will they now take to complete the remaining work?
View Solution
Knowledge Check
- Question 1 - Select One
18 men can complete a work in 9 days. After they have worked for 5 days, 6 more men join them. How many days will they take to complete the remaining work ?
18 पुरुष किसी कार्य को 9 दिनों में पूरा कर सकते हैं | उनके 5 दिनों तक कार्य कर लेने के बाद, 6 अतिरिक्त पुरुष उनके साथ हो गए | शेष कार्य करने में उन्हें कितना समय लगेगा ?A3B212C2D312 - Question 2 - Select One
14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ?
A9 daysB5 daysC6 daysD7 days - Question 3 - Select One
45 men can complete a work in 16 days. Four days after they started working, 36 more men joined them. How many days will they now take to complete the remaining work?
A6 daysB8 daysC623 daysD734 days
12 men can complete a work within 9 days. After 3 days they started the work, 6 men joined them to replace 2 men. How many days will they take to complete the remaining work?
View SolutionThree men can complete a plece of work in 6 days. Two days after they started the work, 3 more men joined them. How many days will they take to complete the remaining work?
View SolutionTwelve men can complete a work in 8 days. Three days after they started the work, 3 more men joined them. In how many days will all of them together complete the remaining work ?
View Solution12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work ?
View Solution60 men can complete a work in 30 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?
View Solution