60 men can complete a work in 30 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?
36
30
40
45
The correct Answer is:C
To solve the problem step by step, we will determine how many days it takes for the work to be completed given the conditions stated in the question.
Step 1: Calculate the total work in units
We know that 60 men can complete the work in 30 days.
- Total work = Number of men × Number of days
- Total work = 60 men × 30 days = 1800 man-days
Step 2: Work done in the first 10 days
In the first 10 days, all 60 men are working.
- Work done in the first 10 days = Number of men × Number of days
- Work done = 60 men × 10 days = 600 units
Step 3: Calculate remaining work after the first 10 days
After the first 10 days, the remaining work is:
- Remaining work = Total work - Work done in the first 10 days
- Remaining work = 1800 units - 600 units = 1200 units
Step 4: Work done in the next 10 days with 50 men
After the first 10 days, 10 men leave, so now 50 men are working.
- Work done in the next 10 days = 50 men × 10 days = 500 units
Step 5: Calculate remaining work after the second 10 days
After the second 10 days, the remaining work is:
- Remaining work = Remaining work - Work done in the second 10 days
- Remaining work = 1200 units - 500 units = 700 units
Step 6: Work done in the next 10 days with 40 men
Another 10 men leave, so now 40 men are working.
- Work done in the next 10 days = 40 men × 10 days = 400 units
Step 7: Calculate remaining work after the third 10 days
After the third 10 days, the remaining work is:
- Remaining work = Remaining work - Work done in the third 10 days
- Remaining work = 700 units - 400 units = 300 units
Step 8: Work done in the next 10 days with 30 men
Another 10 men leave, so now 30 men are working.
- Work done in the next 10 days = 30 men × 10 days = 300 units
Step 9: Calculate remaining work after the fourth 10 days
After the fourth 10 days, the remaining work is:
- Remaining work = Remaining work - Work done in the fourth 10 days
- Remaining work = 300 units - 300 units = 0 units
Step 10: Total days taken to complete the work
Now, we can calculate the total number of days taken:
- Total days = 10 days (first phase) + 10 days (second phase) + 10 days (third phase) + 10 days (fourth phase) = 40 days
Thus, the work was completed in 40 days.
Final Answer:
The work was completed in 40 days.
---
We know that 60 men can complete the work in 30 days.
- Total work = 60 men × 30 days = 1800 man-days
In the first 10 days, all 60 men are working.
- Work done = 60 men × 10 days = 600 units
After the first 10 days, the remaining work is:
- Remaining work = 1800 units - 600 units = 1200 units
After the first 10 days, 10 men leave, so now 50 men are working.
After the second 10 days, the remaining work is:
- Remaining work = 1200 units - 500 units = 700 units
Another 10 men leave, so now 40 men are working.
After the third 10 days, the remaining work is:
- Remaining work = 700 units - 400 units = 300 units
Another 10 men leave, so now 30 men are working.
After the fourth 10 days, the remaining work is:
- Remaining work = 300 units - 300 units = 0 units
Now, we can calculate the total number of days taken:
The work was completed in 40 days.
Similar Questions
25 men can complete a work in 10 days. 20 boys can complete this work in 50 days. 5 men start the work and aftr 10 days 10 boys joined them and remaining work is completed in 20 days. How many boys are joined ?
View Solution24 men can complete a piece of work in 16 days and 18 women can complete the same work in 32 days. 12 men and 6 women work together for 16 days. If the remaining work was to be completed in 2 days, how many additional men would be required besisdes 12 men and 6 women ?
View Solution
Knowledge Check
- Question 1 - Select One
60 men can complete a work in 30 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?
A36B30C40D45 - Question 2 - Select One
50 men can complete a work in 28 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?
A60B30C40D50 - Question 3 - Select One
40 men can complete a work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in
A5623 daysB5313 daysC52 daysD50 days
A can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?
View Solution40 men can complete a work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in
View Solution50 people can complete a work in 50 days. They started the work together but at the end of every 10th day 5 people join the work. In how much time the work would be completed?
View Solution15 men can complete a work in 210 days. They started the work but at the end of 10 days, 15 additional men, with double efficiency, were in- ducted. How many days in all did they take to finish the work ?
View SolutionA and B together can complete a work in 3 days. They started together but after 2 days, B left the work. If the work is completed after 2 more days, Balone could do the work in how many days?
View Solution