A,B,C can do a piece of work individually in 8 10 and 15 days respectively. A and B start working but A quits after working for 2 days. After this ,C joins B till the completion of work . In how many days will the work be completed

A

53/9 days

B

34/7 days

C

85/13 days

D

53/10 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will first determine the work done by A, B, and C individually, then calculate how much work they complete together, and finally find out how long it will take to finish the remaining work.

Step 1: Determine the work rates of A, B, and C
- A can complete the work in 8 days, so A's work rate is 18 of the work per day.
- B can complete the work in 10 days, so B's work rate is 110 of the work per day.
- C can complete the work in 15 days, so C's work rate is 115 of the work per day.

Step 2: Calculate the total work
To make calculations easier, we can find a common multiple of the days. The least common multiple (LCM) of 8, 10, and 15 is 120. Thus, we can consider the total work as 120 units.

Step 3: Calculate the work done by A and B in 2 days
- In one day, A and B together can do:
Work done by A and B in one day=18+110=540+440=940
- Therefore, in 2 days, A and B will complete:
Work done in 2 days=2×940=1840=920 of the work
- The total work is 120 units, so:
Work done in units=920×120=54 units

Step 4: Calculate the remaining work
- Total work = 120 units
- Work done by A and B = 54 units
- Remaining work = 12054=66 units

Step 5: Calculate the work done by B and C together
- B's work rate = 110 units/day
- C's work rate = 115 units/day
- Together, B and C can do:
Work done by B and C in one day=110+115=330+230=530=16 of the work
- In units, this means they can complete:
Work done in units=16×120=20 units per day

Step 6: Calculate the time taken to complete the remaining work
- Remaining work = 66 units
- Time taken by B and C to complete 66 units:
Time=66 units20 units/day=6620=3310 days=3.3 days

Step 7: Calculate the total time taken
- Total time = Time taken by A and B + Time taken by B and C
- Total time = 2 days+3310 days=2010+3310=5310 days=5.3 days

Final Answer
The total time taken to complete the work is 5310 days or 5.3 days.

|


Similar Questions


Knowledge Check

  • A, B and C can do a piece of work individually in 8, 12 and 15
    days, respectively. A and B start working but A quits after
    working for 2 days. After this, C joins B till the completion of
    work. In how many days will the work be completed?

    A588days
    B423days
    C6 days
    D3 days
  • A , B and C can do a piece of work individually in 8 , 12 and 15 days , respectively . A and B start working but A quits after working for 2 days. After this, C joins B till the completion of work. In how many days will the work be completed?

    A589days
    B467days
    C6713days
    D334days
  • A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?

    A5
    B4
    C3
    D2