A,B,C can do a piece of work individually in 8 10 and 15 days respectively. A and B start working but A quits after working for 2 days. After this ,C joins B till the completion of work . In how many days will the work be completed
53/9 days
34/7 days
85/13 days
53/10 days
To solve the problem step by step, we will first determine the work done by A, B, and C individually, then calculate how much work they complete together, and finally find out how long it will take to finish the remaining work.
Step 1: Determine the work rates of A, B, and C
- A can complete the work in 8 days, so A's work rate is 18 of the work per day.
- B can complete the work in 10 days, so B's work rate is 110 of the work per day.
- C can complete the work in 15 days, so C's work rate is 115 of the work per day.
Step 2: Calculate the total work
To make calculations easier, we can find a common multiple of the days. The least common multiple (LCM) of 8, 10, and 15 is 120. Thus, we can consider the total work as 120 units.
Step 3: Calculate the work done by A and B in 2 days
- In one day, A and B together can do:
Work done by A and B in one day=18+110=540+440=940
- Therefore, in 2 days, A and B will complete:
Work done in 2 days=2×940=1840=920 of the work
- The total work is 120 units, so:
Work done in units=920×120=54 units
Step 4: Calculate the remaining work
- Total work = 120 units
- Work done by A and B = 54 units
- Remaining work = 120−54=66 units
Step 5: Calculate the work done by B and C together
- B's work rate = 110 units/day
- C's work rate = 115 units/day
- Together, B and C can do:
Work done by B and C in one day=110+115=330+230=530=16 of the work
- In units, this means they can complete:
Work done in units=16×120=20 units per day
Step 6: Calculate the time taken to complete the remaining work
- Remaining work = 66 units
- Time taken by B and C to complete 66 units:
Time=66 units20 units/day=6620=3310 days=3.3 days
Step 7: Calculate the total time taken
- Total time = Time taken by A and B + Time taken by B and C
- Total time = 2 days+3310 days=2010+3310=5310 days=5.3 days
Final Answer
The total time taken to complete the work is 5310 days or 5.3 days.
- A can complete the work in 8 days, so A's work rate is 18 of the work per day.
- B can complete the work in 10 days, so B's work rate is 110 of the work per day.
- C can complete the work in 15 days, so C's work rate is 115 of the work per day.
To make calculations easier, we can find a common multiple of the days. The least common multiple (LCM) of 8, 10, and 15 is 120. Thus, we can consider the total work as 120 units.
- In one day, A and B together can do:
Work done by A and B in one day=18+110=540+440=940
- Therefore, in 2 days, A and B will complete:
Work done in 2 days=2×940=1840=920 of the work
- The total work is 120 units, so:
Work done in units=920×120=54 units
- Total work = 120 units
- Work done by A and B = 54 units
- Remaining work = 120−54=66 units
- B's work rate = 110 units/day
- C's work rate = 115 units/day
- Together, B and C can do:
Work done by B and C in one day=110+115=330+230=530=16 of the work
- In units, this means they can complete:
Work done in units=16×120=20 units per day
- Remaining work = 66 units
- Time taken by B and C to complete 66 units:
Time=66 units20 units/day=6620=3310 days=3.3 days
- Total time = Time taken by A and B + Time taken by B and C
- Total time = 2 days+3310 days=2010+3310=5310 days=5.3 days
The total time taken to complete the work is 5310 days or 5.3 days.
Similar Questions
A, B and C can do a piece of work individually in 8, 12 and 15 days respectively. A and B start working, but A quits after working for 2 days. After this, C joins B till the completion of work. In how many days will the work be completed ?
View SolutionA, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View Solution
Knowledge Check
A, B and C can do a piece of work individually in 8, 12 and 15
days, respectively. A and B start working but A quits after
working for 2 days. After this, C joins B till the completion of
work. In how many days will the work be completed?A588daysB423daysC6 daysD3 daysA , B and C can do a piece of work individually in 8 , 12 and 15 days , respectively . A and B start working but A quits after working for 2 days. After this, C joins B till the completion of work. In how many days will the work be completed?
A589daysB467daysC6713daysD334daysA,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
A5B4C3D2
A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
View SolutionA and B can do a piece of work in 30 days and 18 days respectively. A started the work alone and then after 6 days B joined him till the completion of the work. In how many days has the whole work completed?
A और B क्रमशः किसी काम को 30 दिन और 18 दिन में पूरा करते है | A किसी काम को अकेले शुरू करता है और छह दिन बाद B उसके साथ काम खत्म होने तक काम करता है | पूरा काम कितने दिन में खत्म होगा ?
View SolutionA, B and C can complete a piece of work in 27 days, 36 days, adn 45 days, respectively. B and C started the work. After 11 days. A joined them. If B left 12 days before its completion, in how many days will the work be completed?
View SolutionA, b and C can alone complete a work in 10, 12 and 15 days
respectively. A and C started the work and after working for
4 days, A left and B joined. In how many days the total work
was completed ?
View SolutionA, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View Solution