A, B and C can do a piece of work individually in 8, 12 and 15 days respectively. A and B start working, but A quits after working for 2 days. After this, C joins B till the completion of work. In how many days will the work be completed ?
589 days
467 days
6713 days
334 days
To solve the problem, we will break it down step by step.
Step 1: Calculate the work done by A, B, and C in one day.
- A can complete the work in 8 days, so A's work in one day = 18
- B can complete the work in 12 days, so B's work in one day = 112
- C can complete the work in 15 days, so C's work in one day = 115
Step 2: Calculate the combined work done by A and B in one day.
- Work done by A and B in one day = 18+112
- To add these fractions, we need a common denominator. The LCM of 8 and 12 is 24.
- 18=324
- 112=224
- So, 18+112=324+224=524
Step 3: Calculate the work done by A and B in 2 days.
- Work done by A and B in 2 days = 2×524=1024=512
Step 4: Calculate the remaining work after A quits.
- Total work = 1 (the whole work)
- Remaining work = Total work - Work done by A and B
- Remaining work = 1−512=1212−512=712
Step 5: Calculate the combined work done by B and C in one day.
- Work done by B and C in one day = 112+115
- The LCM of 12 and 15 is 60.
- 112=560
- 115=460
- So, 112+115=560+460=960=320
Step 6: Calculate the time taken by B and C to complete the remaining work.
- Let N be the number of days B and C take to complete the remaining work.
- Work done in N days = N×320
- We know the remaining work is 712.
- Therefore, N×320=712
Step 7: Solve for N.
- Rearranging gives us:
N=712÷320=712×203=7×2012×3=14036=359
Step 8: Calculate the total time taken to complete the work.
- Total time = Time taken by A and B + Time taken by B and C
- Total time = 2+359
- Converting 2 into ninths gives us 189.
- So, total time = 189+359=539
Final Answer:
- The total time taken to complete the work is 539 days, which is approximately 589 days.
- A can complete the work in 8 days, so A's work in one day = 18
- B can complete the work in 12 days, so B's work in one day = 112
- C can complete the work in 15 days, so C's work in one day = 115
- Work done by A and B in one day = 18+112
- To add these fractions, we need a common denominator. The LCM of 8 and 12 is 24.
- 18=324
- 112=224
- So, 18+112=324+224=524
- Work done by A and B in 2 days = 2×524=1024=512
- Total work = 1 (the whole work)
- Remaining work = Total work - Work done by A and B
- Remaining work = 1−512=1212−512=712
- Work done by B and C in one day = 112+115
- The LCM of 12 and 15 is 60.
- 112=560
- 115=460
- So, 112+115=560+460=960=320
- Let N be the number of days B and C take to complete the remaining work.
- Work done in N days = N×320
- We know the remaining work is 712.
- Therefore, N×320=712
- Rearranging gives us:
N=712÷320=712×203=7×2012×3=14036=359
- Total time = Time taken by A and B + Time taken by B and C
- Total time = 2+359
- Converting 2 into ninths gives us 189.
- So, total time = 189+359=539
- The total time taken to complete the work is 539 days, which is approximately 589 days.
Similar Questions
A,B,C can do a piece of work individually in 8 10 and 15 days respectively. A and B start working but A quits after working for 2 days. After this ,C joins B till the completion of work . In how many days will the work be completed
View SolutionA, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View Solution
Knowledge Check
- Question 1 - Select One
A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
A5B4C3D2 - Question 2 - Select One
A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
A5B4C3D2 - Question 3 - Select One
A and B can do a piece of work in 30 days and 18 days respectively. A started the work alone and then after 6 days B joined him till the completion of the work. In how many days has the whole work completed?
A और B क्रमशः किसी काम को 30 दिन और 18 दिन में पूरा करते है | A किसी काम को अकेले शुरू करता है और छह दिन बाद B उसके साथ काम खत्म होने तक काम करता है | पूरा काम कितने दिन में खत्म होगा ?A12B9C15D17
A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed? 4 b. 15 c. 7 d. 8
View SolutionA, B and C can complete a piece of work in 12, 24 and 36 days respectively. A and B will together complete the same work in how many days?
View SolutionA, b and C can alone complete a work in 10, 12 and 15 days
respectively. A and C started the work and after working for
4 days, A left and B joined. In how many days the total work
was completed ?View SolutionA, B and C can complete a piece of work in 27 days, 36 days, adn 45 days, respectively. B and C started the work. After 11 days. A joined them. If B left 12 days before its completion, in how many days will the work be completed?
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?
View Solution