Doubtnut Promotions Sticky

A, B and C can do a piece of work individually in 8, 12 and 15 days respectively. A and B start working, but A quits after working for 2 days. After this, C joins B till the completion of work. In how many days will the work be completed ?

A

589 days

B

467 days

C

6713 days

D

334 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we will break it down step by step.

Step 1: Calculate the work done by A, B, and C in one day.
- A can complete the work in 8 days, so A's work in one day = 18
- B can complete the work in 12 days, so B's work in one day = 112
- C can complete the work in 15 days, so C's work in one day = 115

Step 2: Calculate the combined work done by A and B in one day.
- Work done by A and B in one day = 18+112
- To add these fractions, we need a common denominator. The LCM of 8 and 12 is 24.
- 18=324
- 112=224
- So, 18+112=324+224=524

Step 3: Calculate the work done by A and B in 2 days.
- Work done by A and B in 2 days = 2×524=1024=512

Step 4: Calculate the remaining work after A quits.
- Total work = 1 (the whole work)
- Remaining work = Total work - Work done by A and B
- Remaining work = 1512=1212512=712

Step 5: Calculate the combined work done by B and C in one day.
- Work done by B and C in one day = 112+115
- The LCM of 12 and 15 is 60.
- 112=560
- 115=460
- So, 112+115=560+460=960=320

Step 6: Calculate the time taken by B and C to complete the remaining work.
- Let N be the number of days B and C take to complete the remaining work.
- Work done in N days = N×320
- We know the remaining work is 712.
- Therefore, N×320=712

Step 7: Solve for N.
- Rearranging gives us:
N=712÷320=712×203=7×2012×3=14036=359

Step 8: Calculate the total time taken to complete the work.
- Total time = Time taken by A and B + Time taken by B and C
- Total time = 2+359
- Converting 2 into ninths gives us 189.
- So, total time = 189+359=539

Final Answer:
- The total time taken to complete the work is 539 days, which is approximately 589 days.

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?

    A5
    B4
    C3
    D2
  • Question 2 - Select One

    A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?

    A5
    B4
    C3
    D2
  • Question 3 - Select One

    A and B can do a piece of work in 30 days and 18 days respectively. A started the work alone and then after 6 days B joined him till the completion of the work. In how many days has the whole work completed?
    A और B क्रमशः किसी काम को 30 दिन और 18 दिन में पूरा करते है | A किसी काम को अकेले शुरू करता है और छह दिन बाद B उसके साथ काम खत्म होने तक काम करता है | पूरा काम कितने दिन में खत्म होगा ?

    A12
    B9
    C15
    D17