A can do a work in 15 days. B is 25% more effcient than a In how many days working together A and B is complete the same work ?
214
257
245
203
The correct Answer is:D
To solve the problem step-by-step, we will follow these calculations:
Step 1: Determine A's Efficiency
A can complete the work in 15 days. The efficiency of A can be calculated as:
Efficiency of A=1 work15 days=115
Step 2: Calculate B's Efficiency
B is 25% more efficient than A. To find B's efficiency, we first convert 25% into a fraction:
25%=25100=14
This means B's efficiency is:
Efficiency of B=Efficiency of A+25% of Efficiency of A=115+14×115
To combine these, we need a common denominator. The least common multiple of 15 and 4 is 60:
Efficiency of A=460,Efficiency of B=1560
So,
Efficiency of B=460+14×460=460+115=460+460=860=215
Step 3: Calculate Total Efficiency
Now, we can find the total efficiency of A and B working together:
Total Efficiency=Efficiency of A+Efficiency of B=460+860=1260=15
Step 4: Calculate Total Work
The total work can be calculated as:
Total Work=Efficiency of A×Days taken by A=115×15=1 work unit
Step 5: Calculate Time Taken by A and B Together
Now, we can find the time taken by A and B together to complete the work:
Time=Total WorkTotal Efficiency=115=5 days
Final Answer
Thus, A and B together will complete the work in 5 days.
---
A can complete the work in 15 days. The efficiency of A can be calculated as:
Efficiency of A=1 work15 days=115
B is 25% more efficient than A. To find B's efficiency, we first convert 25% into a fraction:
25%=25100=14
This means B's efficiency is:
Efficiency of B=Efficiency of A+25% of Efficiency of A=115+14×115
To combine these, we need a common denominator. The least common multiple of 15 and 4 is 60:
Efficiency of A=460,Efficiency of B=1560
So,
Efficiency of B=460+14×460=460+115=460+460=860=215
Now, we can find the total efficiency of A and B working together:
Total Efficiency=Efficiency of A+Efficiency of B=460+860=1260=15
The total work can be calculated as:
Total Work=Efficiency of A×Days taken by A=115×15=1 work unit
Now, we can find the time taken by A and B together to complete the work:
Time=Total WorkTotal Efficiency=115=5 days
Thus, A and B together will complete the work in 5 days.
Similar Questions
Knowledge Check
- Question 1 - Select One
A can complete a piece of work in 12 days. B is 60% more efficient than A. The number of days, that B will take to complete the same work, is
A6B712C8D812 - Question 2 - Select One
A alone can do a work in 15 days. A is 20% less efficient than B. In how many days can B alone do the work?
Aa. 12Bb. 18Cc. 20Dd. 24 - Question 3 - Select One
A can do a piece of work in 24 days. If B is 50% more efficient than A, then in how many days can B do the same work?
A12B16C18D15
A can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?
View SolutionA can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?
View SolutionA can do of a work in 10 days. B can do of the work in 20 days. In how many days can both A and B together do the work?
View SolutionA can do a piece of work in 15 days and B is 25% more efficient than A. If A and B both work for 4 days and after 4 days C can complete the remaining work alone in 8 days, then find time taken by A, B and C together to complete the whole work.
View SolutionA can do a picec of work in 10 days and B is 25% more
efficient than A. In what time will the work be finished if A
and B work together ?View Solution