The efficiences of A , B and C are in ratio 5 : 3 : 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in :
A, B और C की कार्य क्षमता 5 : 3 : 8 है| एक साथ कार्य करते हुए, वे किसी कार्य को 30 दिनों में कर सकते हैं | A और B
ने 20 दिनों तक कार्य किया | शेष कार्य पूरा करने में C को अकेले कितने दिन लगेंगे?
40 days
36 days
30 days
32 days
To solve the problem step by step, we can follow these instructions:
Step 1: Determine the total work done by A, B, and C together.
The efficiencies of A, B, and C are in the ratio of 5:3:8.
Let the efficiencies be:
- Efficiency of A = 5x
- Efficiency of B = 3x
- Efficiency of C = 8x
When they work together, their combined efficiency is:
Total Efficiency=5x+3x+8x=16x
Given that they can complete the work in 30 days, we can calculate the total work (W) using the formula:
W=Efficiency×Time
Thus,
W=16x×30=480x
Step 2: Calculate the work done by A and B in 20 days.
The combined efficiency of A and B is:
Efficiency of A and B=5x+3x=8x
The work done by A and B in 20 days is:
Work done by A and B=Efficiency of A and B×Time
=8x×20=160x
Step 3: Calculate the remaining work.
The remaining work after A and B have worked for 20 days is:
Remaining Work=Total Work−Work done by A and B
=480x−160x=320x
Step 4: Calculate the time taken by C to complete the remaining work.
C's efficiency is 8x. The time (T) taken by C to complete the remaining work is given by:
T=Remaining WorkEfficiency of C
=320x8x=40 days
Final Answer:
C will take 40 days to complete the remaining work alone.
---
The efficiencies of A, B, and C are in the ratio of 5:3:8.
- Efficiency of A = 5x
- Efficiency of B = 3x
- Efficiency of C = 8x
Total Efficiency=5x+3x+8x=16x
W=Efficiency×Time
Thus,
W=16x×30=480x
The combined efficiency of A and B is:
Efficiency of A and B=5x+3x=8x
Work done by A and B=Efficiency of A and B×Time
=8x×20=160x
The remaining work after A and B have worked for 20 days is:
Remaining Work=Total Work−Work done by A and B
=480x−160x=320x
C's efficiency is 8x. The time (T) taken by C to complete the remaining work is given by:
T=Remaining WorkEfficiency of C
=320x8x=40 days
C will take 40 days to complete the remaining work alone.
Topper's Solved these Questions
Similar Questions
The ratio of the efficiencies of A, B and C to do a certain work is 7:3: 5. Working together, they can complete work in 21 days. A and C worked together for 15 days. The remaining work will be completed by B alone in:
A, B और C की कार्य क्षमता का अनुपात 7 : 3 : 5 है | एक साथ कार्य करते हुए, वे किसी कार्य को 21 दिनों में पूरा कर सकते हैं | A और C ने एक साथ 15 दिनों तक कार्य किया | शेष कार्य पूरा करने में B को अकेले कितने दिन लगेंगे ?View SolutionThe ratio of efficiencies of A , B and C is 3 : 5 : 1. Working together, they can complete a piece of work in 5 days. A and B worked together for 3 days. The remaining will be completed by C alone in :
A, B और C की कार्य क्षमता का अनुपात 3 : 5 : 1 है | एक साथ कार्य करते हुए, वे किसी कार्य को 5 दिनों में पूरा कर सकते हैं |A और B ने एक साथ 3 दिनों तक कार्य किया | C को अकेले शेष कार्य करने में कितना समय (दिन) लगेगा ?View Solution
Knowledge Check
- Question 1 - Select One
The efficiencies of A, B and C are in the ratio 5: 3: 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in:
A30 daysB32 daysC36 daysD40 days - Question 2 - Select One
The efficiences of A , B and C are in ratio 5 : 3 : 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in :
A, B और C की कार्य क्षमता 5 : 3 : 8 है| एक साथ कार्य करते हुए, वे किसी कार्य को 30 दिनों में कर सकते हैं | A और B ने 20 दिनों तक कार्य किया | शेष कार्य पूरा करने में C को अकेले कितने दिन लगेंगे?A40 daysB36 daysC30 daysD32 days - Question 3 - Select One
The ratio of the efficiencies of A, B and C is 3: 5:1. Working together, they can complete a piece of work in 5 days. A and B work together for 3 days. The remaining work will be completed by C alone in?
A18 daysB24 daysC21 daysD15 days
To do a certain work, the ratio of the efficiencies of A , B and C is 7 : 5 : 6. Working together, they can complete the same work in 35 days. B and C worked together for 21 days. The remaining work will be completed by A alone in :
एक निश्चित कार्य को करने के लिए,A, B और C की कार्य क्षमता का अनुपात 7 : 5: 6 है| एक साथ कार्य करते हुए, वे इसी कार्य को 35 दिनों में पूरा कर सकते हैं | B और C ने 21 दिनों तक कार्य किया | शेष कार्य पूरा करने में A को अकेले कितने दिन लगेंगे ?View SolutionThe ratio of the efficiencies of A, B and C is 7:5:4. Working together, they can finish work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone:
A, B और C की कार्य क्षमता का अनुपात 7 : 5 : 4 है | एक साथ कार्य करते हुए, वे किसी कार्य को 35 दिनों में समाप्त कर सकते हैं | A और B एक साथ 28 दिनों तक कार्य करते हैं | C शेष कार्य कितने दिनों में पूरा करेगा ?View SolutionThe ratio of efficiencies of A , B and C is 7 : 5 : 8. Working together, they can complete a piece of work in 42 days. B and C worked together for 21 days and the remaining was completed by A alone. The whole work was completed in :
A, B और C की कार्य क्षमता का अनुपात 7 : 5 : 8 है | एक साथ कार्य करते हुए, वे किसी कार्य को 42 दिनों में कर सकते हैं |B और C ने एक साथ 21 दिनों तक कार्य किया और शेष कार्य A ने पूरा किया | पूरा कार्य कितने दिनों में समाप्त हुआ ?View SolutionThe ratio of the efficiencies of A, B and C to do a certain work is 7:3:5. Working together, they can complete the work in 21 days. A and C worked together for 5 days. The remaining work will be completed by B alone in :
View SolutionThe ratio of the efficiencies of A, B and C is 7:5:4. Working together, they can finish work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone:
A, B और C की कार्य क्षमता का अनुपात 7 : 5 : 4 है | एक साथ कार्य करते हुए, वे किसी कार्य को 35 दिनों में समाप्त कर सकते हैं | A और B एक साथ 28 दिनों तक कार्य करते हैं | C शेष कार्य कितने दिनों में पूरा करेगा ?View Solution