A and B can complete a task in 1.5 days. However, A had to leave a few· days before the task was completed and hence 4 it took 2 days in all to complete the task. If A alone could complete the work in 2.625 days, how many days before the work getting over did A leave?
1.125
0.625
0.375
0.875
The correct Answer is:D
To solve the problem step by step, we need to analyze the information given and calculate how many days before the work was completed did A leave.
Step 1: Determine the work done by A and B together
A and B can complete the task in 1.5 days. This means their combined work rate is:
Work rate of A and B=1 task1.5 days=23 tasks per day
Step 2: Calculate the work done by A alone
A alone can complete the task in 2.625 days. Therefore, A's work rate is:
Work rate of A=1 task2.625 days=12.625 tasks per day≈0.38 tasks per day
Step 3: Calculate the work done by B
Since A and B together complete the task at a rate of 23 tasks per day, we can find B's work rate by subtracting A's work rate from their combined work rate:
Work rate of B=23−12.625
To perform this calculation, we first convert 12.625 into a fraction:
12.625=1218=821
Now we need a common denominator to subtract:
23=1421
Thus,
Work rate of B=1421−821=621=27 tasks per day
Step 4: Total work done in 2 days
It is given that the total time taken to complete the task was 2 days. In these 2 days, B completed the remaining work after A left. Since B's work rate is 27 tasks per day, the total work done by B in 2 days is:
Work done by B=2×27=47 tasks
Step 5: Calculate the total work of the task
The total work of the task is 1 (the whole task). Therefore, if B completed 47 of the task, the remaining work done by A and B together before A left is:
Work done by A and B together=1−47=37 tasks
Step 6: Calculate the time A and B worked together
Let x be the time A and B worked together before A left. The work done by A and B together in x days is:
23x=37
To find x, we solve:
x=37÷23=37×32=914 days
Step 7: Calculate the time A left before the work was completed
Since the total time taken to complete the task was 2 days, and A worked for 914 days, the time A left before the work was completed is:
Time A left before completion=2−914=2814−914=1914 days≈1.357 days
Final Calculation
To find how many days before the work was completed A left, we need to subtract the time A worked from the total time:
Days A left before completion=2−914=1914 days≈1.357 days
Conclusion
A left approximately 1.357 days before the work was completed.
A and B can complete the task in 1.5 days. This means their combined work rate is:
Work rate of A and B=1 task1.5 days=23 tasks per day
A alone can complete the task in 2.625 days. Therefore, A's work rate is:
Work rate of A=1 task2.625 days=12.625 tasks per day≈0.38 tasks per day
Since A and B together complete the task at a rate of 23 tasks per day, we can find B's work rate by subtracting A's work rate from their combined work rate:
Work rate of B=23−12.625
To perform this calculation, we first convert 12.625 into a fraction:
12.625=1218=821
Now we need a common denominator to subtract:
23=1421
Thus,
Work rate of B=1421−821=621=27 tasks per day
It is given that the total time taken to complete the task was 2 days. In these 2 days, B completed the remaining work after A left. Since B's work rate is 27 tasks per day, the total work done by B in 2 days is:
Work done by B=2×27=47 tasks
The total work of the task is 1 (the whole task). Therefore, if B completed 47 of the task, the remaining work done by A and B together before A left is:
Work done by A and B together=1−47=37 tasks
Let x be the time A and B worked together before A left. The work done by A and B together in x days is:
23x=37
To find x, we solve:
x=37÷23=37×32=914 days
Since the total time taken to complete the task was 2 days, and A worked for 914 days, the time A left before the work was completed is:
Time A left before completion=2−914=2814−914=1914 days≈1.357 days
To find how many days before the work was completed A left, we need to subtract the time A worked from the total time:
Days A left before completion=2−914=1914 days≈1.357 days
A left approximately 1.357 days before the work was completed.
Similar Questions
A and B can complete a task in 12 days. However, A had to leave a few days before the task was completed and hence it took 16 days in all to complete the task. If A alone could complete the work in 21 days, how many days before the work getting over did A leave?
View SolutionA and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?
View Solution
Knowledge Check
- Question 1 - Select One
A and B can complete a task in 1.5 days. However, A had to leave a few days before the task was completed and hence it took 2 days in all to complete the task. If A alone could complete the work in 2.625 days, how many days before the work getting over did A leave?
A1.125B0.625C0.375D0.875 - Question 2 - Select One
A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16 - Question 3 - Select One
A and B together can complete a particular task in 8 days. If
B alone can complete the same task in 10 days, how many
days will A take to complete the task if he works alone ?A28B36C40D32
A and B together can complete a task in 12 days. However, if A works alone, completes half the job and leaves and then B works alone and completes the rest of the work, it takes 25 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?
View SolutionA can complete a task alone in 8 days, while B takes 12 days to do it by herself. Together with C it takes them 4 days to complete the work. If C and D together can complete the task in 15 days, then how many days will D need to complete the task by herself?
View SolutionA and B can complete a task in 25 days. B alone can complete 3313% of the same task in 15 days. In how many days can A alone complete 415th of the same task? /
A और B किसी कार्य को 25 दिनों में पूरा कर सकते हैं | B इसी कार्य का 3313% भाग अकेले 15 दिनों में पूरा कर सकता है। A इस कार्य का 415th भाग कितने दिनों में पूरा करेगा ?View SolutionA can complete a task alone in 9 days while B takes 13.5 days to do it by herself . Together with C it takes them 4.5 days to complete the task . If C and D together can complete the task in 18 days , then how many days will D need to complete the task by herself ?
View SolutionX can complete a task in 8 days, whereas Y can complete the same task in 10 days. If they work together, in how many days will the task be completed?
View Solution