Doubtnut Promotions Sticky

A and B can complete a task in 1.5 days. However, A had to leave a few· days before the task was completed and hence 4 it took 2 days in all to complete the task. If A alone could complete the work in 2.625 days, how many days before the work getting over did A leave?

A

1.125

B

0.625

C

0.375

D

0.875

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we need to analyze the information given and calculate how many days before the work was completed did A leave.

Step 1: Determine the work done by A and B together
A and B can complete the task in 1.5 days. This means their combined work rate is:
Work rate of A and B=1 task1.5 days=23 tasks per day

Step 2: Calculate the work done by A alone
A alone can complete the task in 2.625 days. Therefore, A's work rate is:
Work rate of A=1 task2.625 days=12.625 tasks per day0.38 tasks per day

Step 3: Calculate the work done by B
Since A and B together complete the task at a rate of 23 tasks per day, we can find B's work rate by subtracting A's work rate from their combined work rate:
Work rate of B=2312.625
To perform this calculation, we first convert 12.625 into a fraction:
12.625=1218=821
Now we need a common denominator to subtract:
23=1421
Thus,
Work rate of B=1421821=621=27 tasks per day

Step 4: Total work done in 2 days
It is given that the total time taken to complete the task was 2 days. In these 2 days, B completed the remaining work after A left. Since B's work rate is 27 tasks per day, the total work done by B in 2 days is:
Work done by B=2×27=47 tasks

Step 5: Calculate the total work of the task
The total work of the task is 1 (the whole task). Therefore, if B completed 47 of the task, the remaining work done by A and B together before A left is:
Work done by A and B together=147=37 tasks

Step 6: Calculate the time A and B worked together
Let x be the time A and B worked together before A left. The work done by A and B together in x days is:
23x=37
To find x, we solve:
x=37÷23=37×32=914 days

Step 7: Calculate the time A left before the work was completed
Since the total time taken to complete the task was 2 days, and A worked for 914 days, the time A left before the work was completed is:
Time A left before completion=2914=2814914=1914 days1.357 days

Final Calculation
To find how many days before the work was completed A left, we need to subtract the time A worked from the total time:
Days A left before completion=2914=1914 days1.357 days

Conclusion
A left approximately 1.357 days before the work was completed.

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can complete a task in 1.5 days. However, A had to leave a few days before the task was completed and hence it took 2 days in all to complete the task. If A alone could complete the work in 2.625 days, how many days before the work getting over did A leave?

    A1.125
    B0.625
    C0.375
    D0.875
  • Question 2 - Select One

    A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?

    A4
    B15
    C154
    D16
  • Question 3 - Select One

    A and B together can complete a particular task in 8 days. If
    B alone can complete the same task in 10 days, how many
    days will A take to complete the task if he works alone ?

    A28
    B36
    C40
    D32