A can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?
6
5
7
7.2
The correct Answer is:A
To solve the problem, we need to determine how many days A and B worked together before A leaves 3 days before the work is completed. Here’s a step-by-step solution:
Step 1: Determine the total work
A can complete the work in 12 days, and B can complete it in 18 days. To find the total work, we can use the least common multiple (LCM) of the two times.
Calculation:
- LCM of 12 and 18 is 36.
Hint: The LCM gives us a common measure of total work that both A and B can complete.
Step 2: Calculate the work done by A and B in one day
Now, we calculate how much work A and B can do in one day.
Calculation:
- Work done by A in one day = Total work / Days taken by A = 36 / 12 = 3
- Work done by B in one day = Total work / Days taken by B = 36 / 18 = 2
Hint: The work done in one day is found by dividing the total work by the number of days each person takes to complete the work.
Step 3: Calculate the total work done by B alone in the last 3 days
Since A leaves 3 days before the work is completed, we need to calculate how much work B does alone in those 3 days.
Calculation:
- Work done by B in 3 days = Work done by B in one day × 3 = 2 × 3 = 6
Hint: To find the work done by one person over multiple days, multiply the daily work by the number of days.
Step 4: Calculate the remaining work after B's contribution
Now, we need to find out how much work was done by A and B together before A left.
Calculation:
- Total work = 36
- Work done by B in the last 3 days = 6
- Remaining work done by A and B together = Total work - Work done by B = 36 - 6 = 30
Hint: Subtract the work done by B alone from the total work to find out how much work was completed while A was still present.
Step 5: Calculate the total work done together in one day
Now, we calculate how much work A and B do together in one day.
Calculation:
- Total work done together in one day = Work done by A + Work done by B = 3 + 2 = 5
Hint: The combined daily work rate is the sum of the individual daily work rates.
Step 6: Calculate the number of days they worked together
Finally, we can find out how many days A and B worked together by dividing the remaining work by their combined daily work.
Calculation:
- Days worked together = Remaining work / Combined daily work = 30 / 5 = 6
Hint: To find the number of days worked together, divide the remaining work by the total work done together in one day.
Conclusion
A and B worked together for 6 days.
A can complete the work in 12 days, and B can complete it in 18 days. To find the total work, we can use the least common multiple (LCM) of the two times.
- LCM of 12 and 18 is 36.
Now, we calculate how much work A and B can do in one day.
- Work done by A in one day = Total work / Days taken by A = 36 / 12 = 3
- Work done by B in one day = Total work / Days taken by B = 36 / 18 = 2
Since A leaves 3 days before the work is completed, we need to calculate how much work B does alone in those 3 days.
- Work done by B in 3 days = Work done by B in one day × 3 = 2 × 3 = 6
Now, we need to find out how much work was done by A and B together before A left.
- Total work = 36
- Work done by B in the last 3 days = 6
- Remaining work done by A and B together = Total work - Work done by B = 36 - 6 = 30
Now, we calculate how much work A and B do together in one day.
- Total work done together in one day = Work done by A + Work done by B = 3 + 2 = 5
Finally, we can find out how many days A and B worked together by dividing the remaining work by their combined daily work.
- Days worked together = Remaining work / Combined daily work = 30 / 5 = 6
A and B worked together for 6 days.
Similar Questions
A can do a work in 15 days and B can do the same in 25 days. If they start the work together and B leaves 7 days before completion of the work then the work will be completed in how many days?
View SolutionA can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?
View Solution
Knowledge Check
A and B can do a piece of work together in 15 days while A alone can do it in 25 days. They start working together but B leaves 5 days before the completion of the work. For how many days did A and B work together?
A10B12C9D11A and B can complete a task together in 15 days, while A alone can complete it in 18.75 days. They start working together but A leaves 12.5 days before the completion of the work. For how many days did A and B work together ?
A10B13.75C12.5D11.25A can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?
A10B8C12D9
A can do a work in 25 days and B can do the same work in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the work?
View SolutionA can do a work in 45 days and B can do it in 40 days. Both starts the work together and after some days Aleaves the work. If the work is completed in 32 days, then for how many days A worked?
View SolutionIf A alone can do a work in 12 days and B alone can do it in 8 days, Working together, in how many days will they complete it?
View SolutionA can do a work in 20 days. A and B can do it in 12 days together. In how many days B can do it alone?
View SolutionKrishna can do a work in 10 days while Mohan can do the same work in 20 days. They started work together. After 3 days Krishna left the work and Mohan completed it. For how many days Mohan worked alone more than the number of days required when both worked together ?
View Solution