A can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?

A

6

B

5

C

7

D

7.2

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem, we need to determine how many days A and B worked together before A leaves 3 days before the work is completed. Here’s a step-by-step solution:

Step 1: Determine the total work
A can complete the work in 12 days, and B can complete it in 18 days. To find the total work, we can use the least common multiple (LCM) of the two times.

Calculation:
- LCM of 12 and 18 is 36.

Hint: The LCM gives us a common measure of total work that both A and B can complete.

Step 2: Calculate the work done by A and B in one day
Now, we calculate how much work A and B can do in one day.

Calculation:
- Work done by A in one day = Total work / Days taken by A = 36 / 12 = 3
- Work done by B in one day = Total work / Days taken by B = 36 / 18 = 2

Hint: The work done in one day is found by dividing the total work by the number of days each person takes to complete the work.

Step 3: Calculate the total work done by B alone in the last 3 days
Since A leaves 3 days before the work is completed, we need to calculate how much work B does alone in those 3 days.

Calculation:
- Work done by B in 3 days = Work done by B in one day × 3 = 2 × 3 = 6

Hint: To find the work done by one person over multiple days, multiply the daily work by the number of days.

Step 4: Calculate the remaining work after B's contribution
Now, we need to find out how much work was done by A and B together before A left.

Calculation:
- Total work = 36
- Work done by B in the last 3 days = 6
- Remaining work done by A and B together = Total work - Work done by B = 36 - 6 = 30

Hint: Subtract the work done by B alone from the total work to find out how much work was completed while A was still present.

Step 5: Calculate the total work done together in one day
Now, we calculate how much work A and B do together in one day.

Calculation:
- Total work done together in one day = Work done by A + Work done by B = 3 + 2 = 5

Hint: The combined daily work rate is the sum of the individual daily work rates.

Step 6: Calculate the number of days they worked together
Finally, we can find out how many days A and B worked together by dividing the remaining work by their combined daily work.

Calculation:
- Days worked together = Remaining work / Combined daily work = 30 / 5 = 6

Hint: To find the number of days worked together, divide the remaining work by the total work done together in one day.

Conclusion
A and B worked together for 6 days.

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A and B can do a piece of work together in 15 days while A alone can do it in 25 days. They start working together but B leaves 5 days before the completion of the work. For how many days did A and B work together?

    A10
    B12
    C9
    D11
  • A and B can complete a task together in 15 days, while A alone can complete it in 18.75 days. They start working together but A leaves 12.5 days before the completion of the work. For how many days did A and B work together ?

    A10
    B13.75
    C12.5
    D11.25
  • A can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?

    A10
    B8
    C12
    D9