A and B can complete a task in 1.5 days. However, A had to leave a few days before the task was completed and hence it took 2 days in all to complete the task. If A alone could complete the work in 2.625 days, how many days before the work getting over did A leave?
1.125
0.625
0.375
0.875
The correct Answer is:D
To solve the problem step by step, let's break it down:
Step 1: Determine the efficiency of A and B together
A and B can complete the task in 1.5 days. Therefore, their combined work rate (efficiency) is:
Efficiency of A + B=11.5=23 (work per day)
Step 2: Determine the efficiency of A alone
A can complete the task in 2.625 days. Therefore, A's efficiency is:
Efficiency of A=12.625=821 (work per day)
Step 3: Calculate the efficiency of B
Using the combined efficiency of A and B, we can find B's efficiency:
Efficiency of B=Efficiency of A + B−Efficiency of A
Efficiency of B=23−821
To perform this subtraction, we need a common denominator. The least common multiple of 3 and 21 is 21:
23=1421
Now, substituting back:
Efficiency of B=1421−821=621=27 (work per day)
Step 4: Determine how long A worked
Let A work for x days. Since the total time taken to complete the task is 2 days, B worked for 2−x days. The total work done can be expressed as:
Work done by A+Work done by B=1 (complete work)
(821⋅x)+(27⋅(2−x))=1
Step 5: Simplify the equation
First, express 27 in terms of a common denominator with 821:
27=621
Now substitute this back into the equation:
821x+621(2−x)=1
Multiply through by 21 to eliminate the fraction:
8x+6(2−x)=21
Distributing gives:
8x+12−6x=21
Combine like terms:
2x+12=21
Subtract 12 from both sides:
2x=9
Divide by 2:
x=4.5
Step 6: Calculate how long A left before the work was completed
Since the total time taken is 2 days, we find how long before the end A left:
Time A left=2−x=2−1.125=0.875 days
Final Answer
A left 0.875 days before the work was completed.
---
A and B can complete the task in 1.5 days. Therefore, their combined work rate (efficiency) is:
Efficiency of A + B=11.5=23 (work per day)
A can complete the task in 2.625 days. Therefore, A's efficiency is:
Efficiency of A=12.625=821 (work per day)
Using the combined efficiency of A and B, we can find B's efficiency:
Efficiency of B=Efficiency of A + B−Efficiency of A
Efficiency of B=23−821
To perform this subtraction, we need a common denominator. The least common multiple of 3 and 21 is 21:
23=1421
Now, substituting back:
Efficiency of B=1421−821=621=27 (work per day)
Let A work for x days. Since the total time taken to complete the task is 2 days, B worked for 2−x days. The total work done can be expressed as:
Work done by A+Work done by B=1 (complete work)
(821⋅x)+(27⋅(2−x))=1
First, express 27 in terms of a common denominator with 821:
27=621
Now substitute this back into the equation:
821x+621(2−x)=1
Multiply through by 21 to eliminate the fraction:
8x+6(2−x)=21
Distributing gives:
8x+12−6x=21
Combine like terms:
2x+12=21
Subtract 12 from both sides:
2x=9
Divide by 2:
x=4.5
Since the total time taken is 2 days, we find how long before the end A left:
Time A left=2−x=2−1.125=0.875 days
A left 0.875 days before the work was completed.
Similar Questions
A and B can complete a task in 12 days. However, A had to leave a few days before the task was completed and hence it took 16 days in all to complete the task. If A alone could complete the work in 21 days, how many days before the work getting over did A leave?
View SolutionA and B together can complete a task in 12 days. However, if A works alone, completes half the job and leaves and then B works alone and completes the rest of the work, it takes 25 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?
View Solution
Knowledge Check
- Question 1 - Select One
A and B can complete a task in 1.5 days. However, A had to leave a few· days before the task was completed and hence 4 it took 2 days in all to complete the task. If A alone could complete the work in 2.625 days, how many days before the work getting over did A leave?
A1.125B0.625C0.375D0.875 - Question 2 - Select One
A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16 - Question 3 - Select One
A and B can complete a task in 25 days. B alone can complete 3313% of the same task in 15 days. In how many days can A alone complete 415th of the same task? /
A और B किसी कार्य को 25 दिनों में पूरा कर सकते हैं | B इसी कार्य का 3313% भाग अकेले 15 दिनों में पूरा कर सकता है। A इस कार्य का 415th भाग कितने दिनों में पूरा करेगा ?A15B10C18D12
A can complete a task alone in 8 days, while B takes 12 days to do it by herself. Together with C it takes them 4 days to complete the work. If C and D together can complete the task in 15 days, then how many days will D need to complete the task by herself?
View SolutionA and B together can complete a particular task in 8 days. If
B alone can complete the same task in 10 days, how many
days will A take to complete the task if he works alone ?View SolutionA can complete a task alone in 9 days while B takes 13.5 days to do it by herself . Together with C it takes them 4.5 days to complete the task . If C and D together can complete the task in 18 days , then how many days will D need to complete the task by herself ?
View SolutionX can complete a task in 8 days, whereas Y can complete the same task in 10 days. If they work together, in how many days will the task be completed?
View SolutionA and B together can complete a task in 10 days, B and C can do in 15 days, and C and A together can do it in 12 days. How long will they take to complete the task working together?
View Solution