A and B can complete a task in 1.5 days. However, A had to leave a few days before the task was completed and hence it took 2 days in all to complete the task. If A alone could complete the work in 2.625 days, how many days before the work getting over did A leave?
1.125
0.625
0.375
0.875
The correct Answer is:D
Step by step video, text & image solution for A and B can complete a task in 1.5 days. However, A had to leave a few days before the task was completed and hence it took 2 days in all to complete the task. If A alone could complete the work in 2.625 days, how many days before the work getting over did A leave? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Similar Questions
A and B can complete a task in 12 days. However, A had to leave a few days before the task was completed and hence it took 16 days in all to complete the task. If A alone could complete the work in 21 days, how many days before the work getting over did A leave?
View SolutionA and B together can complete a task in 12 days. However, if A works alone, completes half the job and leaves and then B works alone and completes the rest of the work, it takes 25 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?
View Solution
Knowledge Check
- Question 1 - Select One
A and B can complete a task in 1.5 days. However, A had to leave a few┬╖ days before the task was completed and hence 4 it took 2 days in all to complete the task. If A alone could complete the work in 2.625 days, how many days before the work getting over did A leave?
A1.125B0.625C0.375D0.875 - Question 2 - Select One
A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16 - Question 3 - Select One
A and B can complete a task in 25 days. B alone can complete 3313% of the same task in 15 days. In how many days can A alone complete 415th of the same task? /
A рдФрд░ B рдХрд┐рд╕реА рдХрд╛рд░реНрдп рдХреЛ 25 рджрд┐рдиреЛрдВ рдореЗрдВ рдкреВрд░рд╛ рдХрд░ рд╕рдХрддреЗ рд╣реИрдВ | B рдЗрд╕реА рдХрд╛рд░реНрдп рдХрд╛ 3313% рднрд╛рдЧ рдЕрдХреЗрд▓реЗ 15 рджрд┐рдиреЛрдВ рдореЗрдВ рдкреВрд░рд╛ рдХрд░ рд╕рдХрддрд╛ рд╣реИред A рдЗрд╕ рдХрд╛рд░реНрдп рдХрд╛ 415th рднрд╛рдЧ рдХрд┐рддрдиреЗ рджрд┐рдиреЛрдВ рдореЗрдВ рдкреВрд░рд╛ рдХрд░реЗрдЧрд╛ ?A15B10C18D12
A can complete a task alone in 8 days, while B takes 12 days to do it by herself. Together with C it takes them 4 days to complete the work. If C and D together can complete the task in 15 days, then how many days will D need to complete the task by herself?
View SolutionA and B together can complete a particular task in 8 days. If
B alone can complete the same task in 10 days, how many
days will A take to complete the task if he works alone ?View SolutionA can complete a task alone in 9 days while B takes 13.5 days to do it by herself . Together with C it takes them 4.5 days to complete the task . If C and D together can complete the task in 18 days , then how many days will D need to complete the task by herself ?
View SolutionX can complete a task in 8 days, whereas Y can complete the same task in 10 days. If they work together, in how many days will the task be completed?
View SolutionA and B together can complete a task in 10 days, B and C can do in 15 days, and C and A together can do it in 12 days. How long will they take to complete the task working together?
View Solution