Two persons A and B can complete a task in 10 days and 15 days, respectively. They work together and A leaves 5 days before the task is completed After that, B alone completes the remaining task The number of days taken to complete the whole task is :
8
9
10
12
The correct Answer is:B
Step by step video, text & image solution for Two persons A and B can complete a task in 10 days and 15 days, respectively. They work together and A leaves 5 days before the task is completed After that, B alone completes the remaining task The number of days taken to complete the whole task is : by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
- BOOK - SSC SELECTION POSTCHAPTER - SSC SELECTION POST (14 DEC 2020) SHIFT 1 MATRICULATION LEVEL EXERCISE - Quantitative Aptitude25videos
SSC SELECTION POST (14 DEC 2020) SHIFT 1 MATRICULATION LEVEL
- BOOK - SSC SELECTION POSTCHAPTER - SSC SELECTION POST (9 NOV 2020 SHIFT 1 HSC)EXERCISE - MULTIPLE CHOICE QUESTIONS25videos
SSC SELECTION POST (9 NOV 2020 SHIFT 1 HSC)
Similar Questions
A can complete a work in 12 days, B in 15 days. Find the time taken by them: if A leaves two days before the actual completion of the work.
View SolutionA can complete a work in 12 days, B in 15 days. Find the time taken by them: if B leaves two days before the scheduled completion of the work.
View Solution
Knowledge Check
- Question 1 - Select One
A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?
A6B8C5D10 - Question 2 - Select One
A and B can complete a work in 12 days and 15 days respectively. They started the work together. If after 4 days A leaves the job, then in how many days B will complete the remaining work?
A2 daysB3 daysC4 daysD112 days - Question 3 - Select One
Smith and Ajit can complete a task in 12 days and 18 days respectively. If they work together on a task for 4 days, then the fraction of task that will be left is:
A49B19C29D59
A can complete a work in 15 days, B in 18 days. Find the time taken by them: if A leaves two days before the scheduled completion of the work.
View SolutionA and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in:
View SolutionRam and Mohan can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days Mohan had to leave and Ram alone completed the remaining work The whole work was completed in:
View SolutionA and B can complete a task in 40 days and 16 days respectively. A started the task alone and then after 12 days B joined him till the completion of the task. How long did the task last after B joined the task?
View SolutionA, B, and C can alone do a task in 40, 120 and 36 days, respectively. A and B together work for 20 days and leave the task incomplete. C resumes it an complete it alone. How many days did C take to complete it?
View Solution