Vaibhav can do a piece of work in 60 days. He works there for 15 days and then Sandeep alone finishes the remaining work in 30 days. In how many days will Vaibhav and Sandeep working together finish the work?

A

20 days

B

24 days

C

18 days

D

22 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we need to determine how long it will take for Vaibhav and Sandeep to complete the work together.

Step 1: Determine Vaibhav's Work Rate
Vaibhav can complete the work in 60 days. Therefore, his work rate is:
Vaibhav's work rate=160 (work per day)

Step 2: Calculate Work Done by Vaibhav in 15 Days
In 15 days, the amount of work Vaibhav completes is:
Work done by Vaibhav in 15 days=15×160=1560=14

Step 3: Determine Remaining Work
The total work is considered as 1 unit. After Vaibhav has completed 14 of the work, the remaining work is:
Remaining work=114=34

Step 4: Determine Sandeep's Work Rate
Sandeep finishes the remaining 34 of the work in 30 days. Therefore, his work rate is:
Sandeep's work rate=3430=3120=140 (work per day)

Step 5: Combined Work Rate of Vaibhav and Sandeep
When Vaibhav and Sandeep work together, their combined work rate is:
Combined work rate=Vaibhav's work rate+Sandeep's work rate=160+140

To add these fractions, we need a common denominator. The least common multiple of 60 and 40 is 120. Thus:
160=2120,140=3120
Combined work rate=2120+3120=5120=124 (work per day)

Step 6: Calculate Time Taken to Complete the Work Together
To find out how many days it will take for Vaibhav and Sandeep to complete the entire work together, we take the reciprocal of their combined work rate:
Time taken=1Combined work rate=1124=24 days

Final Answer
Vaibhav and Sandeep working together will finish the work in 24 days.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A can do a piece of work in 60 days. He works for 15 days and then B alone finishes the remaining work in 30 days. The two together can finish the work in

    A24 days
    B25 days
    C30 days
    D32 days
  • A can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?

    A24
    B18
    C36
    D42
  • P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?

    A10
    B16
    C15
    D20