Vaibhav can do a piece of work in 60 days. He works there for 15 days and then Sandeep alone finishes the remaining work in 30 days. In how many days will Vaibhav and Sandeep working together finish the work?
20 days
24 days
18 days
22 days
The correct Answer is:B
To solve the problem step by step, we need to determine how long it will take for Vaibhav and Sandeep to complete the work together.
Step 1: Determine Vaibhav's Work Rate
Vaibhav can complete the work in 60 days. Therefore, his work rate is:
Vaibhav's work rate=160 (work per day)
Step 2: Calculate Work Done by Vaibhav in 15 Days
In 15 days, the amount of work Vaibhav completes is:
Work done by Vaibhav in 15 days=15×160=1560=14
Step 3: Determine Remaining Work
The total work is considered as 1 unit. After Vaibhav has completed 14 of the work, the remaining work is:
Remaining work=1−14=34
Step 4: Determine Sandeep's Work Rate
Sandeep finishes the remaining 34 of the work in 30 days. Therefore, his work rate is:
Sandeep's work rate=3430=3120=140 (work per day)
Step 5: Combined Work Rate of Vaibhav and Sandeep
When Vaibhav and Sandeep work together, their combined work rate is:
Combined work rate=Vaibhav's work rate+Sandeep's work rate=160+140
To add these fractions, we need a common denominator. The least common multiple of 60 and 40 is 120. Thus:
160=2120,140=3120
Combined work rate=2120+3120=5120=124 (work per day)
Step 6: Calculate Time Taken to Complete the Work Together
To find out how many days it will take for Vaibhav and Sandeep to complete the entire work together, we take the reciprocal of their combined work rate:
Time taken=1Combined work rate=1124=24 days
Final Answer
Vaibhav and Sandeep working together will finish the work in 24 days.
---
Vaibhav can complete the work in 60 days. Therefore, his work rate is:
Vaibhav's work rate=160 (work per day)
In 15 days, the amount of work Vaibhav completes is:
Work done by Vaibhav in 15 days=15×160=1560=14
The total work is considered as 1 unit. After Vaibhav has completed 14 of the work, the remaining work is:
Remaining work=1−14=34
Sandeep finishes the remaining 34 of the work in 30 days. Therefore, his work rate is:
Sandeep's work rate=3430=3120=140 (work per day)
When Vaibhav and Sandeep work together, their combined work rate is:
Combined work rate=Vaibhav's work rate+Sandeep's work rate=160+140
160=2120,140=3120
Combined work rate=2120+3120=5120=124 (work per day)
To find out how many days it will take for Vaibhav and Sandeep to complete the entire work together, we take the reciprocal of their combined work rate:
Time taken=1Combined work rate=1124=24 days
Vaibhav and Sandeep working together will finish the work in 24 days.
Similar Questions
A can do a piece of work in 80 days.He works at it for 10 days and then B alore finishes the remaining work in 42 days.How long will B take to do the entire work alone?
View SolutionA can do a piece of work in 30 days. He worked for 6 days and B finished the remaining work in 48 days. B alone can do the whole work in how many days?
View Solution
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 60 days. He works for 15 days and then B alone finishes the remaining work in 30 days. The two together can finish the work in
A24 daysB25 daysC30 daysD32 days - Question 2 - Select One or More
A can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?
A24B18C36D42 - Question 3 - Select One
P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?
A10B16C15D20
A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
View SolutionA can do a piece of work in 30 days and B can do the same piece of work in 20 days. They start working together and work for 4 days and then both leave the work. C alone finishes the remaining work in 18 days. In how many days will C alone finish the whole work?
View SolutionA can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave the work. Then Calone finIshes the remaining work in 10 days. In how many days will finish the full work?
View SolutionX and Y can do a piece of work in 30 days. They work together for 6 days and thenX quits and Y finishes the work in 32 days . In how many days can Y do the piece of work alone ?
View SolutionA can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in
View Solution