A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in

A

16 days

B

24 days

C

28 days

D

29 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, let's break it down:

Step 1: Determine A's Efficiency
A can complete the work in 18 days. We can assume that the total work is 1800 units (for easier calculations). Thus, A's efficiency can be calculated as:
Efficiency of A=Total WorkTime taken by A=1800 units18 days=100 units/day

Hint: To find efficiency, divide the total work by the time taken to complete that work.

Step 2: Calculate Work Done by A in 12 Days
A worked for 12 days. The amount of work done by A in these 12 days is:
Work done by A=Efficiency of A×Days worked=100 units/day×12 days=1200 units

Hint: Multiply the efficiency by the number of days worked to find the total work done.

Step 3: Calculate Remaining Work
The total work is 1800 units, and A has completed 1200 units. Therefore, the remaining work is:
Remaining Work=Total WorkWork done by A=1800 units1200 units=600 units

Hint: Subtract the work done from the total work to find out how much is left.

Step 4: Determine B's Efficiency
B finished the remaining 600 units of work in 8 days. Therefore, B's efficiency can be calculated as:
Efficiency of B=Remaining WorkTime taken by B=600 units8 days=75 units/day

Hint: To find efficiency, divide the amount of work completed by the time taken to complete that work.

Step 5: Calculate Time for B to Complete the Whole Work Alone
Now, we need to find out how long it would take B to complete the entire 1800 units of work alone. We can use the efficiency of B:
Time taken by B to complete the whole work=Total WorkEfficiency of B=1800 units75 units/day=24 days

Hint: To find the time taken to complete the whole work, divide the total work by the efficiency.

Conclusion
B alone can complete the whole work in 24 days.

Final Answer
B alone can do the whole work in 24 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do a piece of work in 30 days. He worked for 6 days and B finished the remaining work in 48 days. B alone can do the whole work in how many days?

    A60
    B55
    C75
    D70
  • A can do a piece of work in 20 days. He worked for 5 days and B finished the remaining work in 42 days. B alone can do the whole work in how many days?

    Aa)56
    Bb)52
    Cc)46
    Dd)64
  • A can do a piece of work in 60 days. He works for 15 days and then B alone finishes the remaining work in 30 days. The two together can finish the work in

    A24 days
    B25 days
    C30 days
    D32 days