A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in
16 days
24 days
28 days
29 days
The correct Answer is:B
To solve the problem step by step, let's break it down:
Step 1: Determine A's Efficiency
A can complete the work in 18 days. We can assume that the total work is 1800 units (for easier calculations). Thus, A's efficiency can be calculated as:
Efficiency of A=Total WorkTime taken by A=1800 units18 days=100 units/day
Hint: To find efficiency, divide the total work by the time taken to complete that work.
Step 2: Calculate Work Done by A in 12 Days
A worked for 12 days. The amount of work done by A in these 12 days is:
Work done by A=Efficiency of A×Days worked=100 units/day×12 days=1200 units
Hint: Multiply the efficiency by the number of days worked to find the total work done.
Step 3: Calculate Remaining Work
The total work is 1800 units, and A has completed 1200 units. Therefore, the remaining work is:
Remaining Work=Total Work−Work done by A=1800 units−1200 units=600 units
Hint: Subtract the work done from the total work to find out how much is left.
Step 4: Determine B's Efficiency
B finished the remaining 600 units of work in 8 days. Therefore, B's efficiency can be calculated as:
Efficiency of B=Remaining WorkTime taken by B=600 units8 days=75 units/day
Hint: To find efficiency, divide the amount of work completed by the time taken to complete that work.
Step 5: Calculate Time for B to Complete the Whole Work Alone
Now, we need to find out how long it would take B to complete the entire 1800 units of work alone. We can use the efficiency of B:
Time taken by B to complete the whole work=Total WorkEfficiency of B=1800 units75 units/day=24 days
Hint: To find the time taken to complete the whole work, divide the total work by the efficiency.
Conclusion
B alone can complete the whole work in 24 days.
Final Answer
B alone can do the whole work in 24 days.
---
A can complete the work in 18 days. We can assume that the total work is 1800 units (for easier calculations). Thus, A's efficiency can be calculated as:
Efficiency of A=Total WorkTime taken by A=1800 units18 days=100 units/day
A worked for 12 days. The amount of work done by A in these 12 days is:
Work done by A=Efficiency of A×Days worked=100 units/day×12 days=1200 units
The total work is 1800 units, and A has completed 1200 units. Therefore, the remaining work is:
Remaining Work=Total Work−Work done by A=1800 units−1200 units=600 units
B finished the remaining 600 units of work in 8 days. Therefore, B's efficiency can be calculated as:
Efficiency of B=Remaining WorkTime taken by B=600 units8 days=75 units/day
Now, we need to find out how long it would take B to complete the entire 1800 units of work alone. We can use the efficiency of B:
Time taken by B to complete the whole work=Total WorkEfficiency of B=1800 units75 units/day=24 days
B alone can complete the whole work in 24 days.
B alone can do the whole work in 24 days.
Topper's Solved these Questions
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-II45videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-III31videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI74videos
TIME AND DISTANCE
- BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF25videos
TRIGONOMETRY
Similar Questions
A can do a piece of work in 80 days.He works at it for 10 days and then B alore finishes the remaining work in 42 days.How long will B take to do the entire work alone?
View SolutionA can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in
View Solution
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 30 days. He worked for 6 days and B finished the remaining work in 48 days. B alone can do the whole work in how many days?
A60B55C75D70 - Question 2 - Select One
A can do a piece of work in 20 days. He worked for 5 days and B finished the remaining work in 42 days. B alone can do the whole work in how many days?
Aa)56Bb)52Cc)46Dd)64 - Question 3 - Select One
A can do a piece of work in 60 days. He works for 15 days and then B alone finishes the remaining work in 30 days. The two together can finish the work in
A24 daysB25 daysC30 daysD32 days
Vaibhav can do a piece of work in 60 days. He works there for 15 days and then Sandeep alone finishes the remaining work in 30 days. In how many days will Vaibhav and Sandeep working together finish the work?
View SolutionA can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
View SolutionA can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in
View SolutionAbhishek can do a piece of work in 40 days. He alone worked at it for 8 days and then Bacchhan completed alone the rest work in 24 days. In how many days they will complete the whole work, working together ?
View SolutionAbhishek can do a piece of work in 40 days. He alone worked at it for 8 days and then Bacchhan completed alone the rest work in 24 days. In how many days they will complete the whole work, working together?
View Solution