Doubtnut Promotions Sticky

Efficiency of B is 40% more than efficiency of A and efficiency of C is 150% of efficiency of B. B alone can complete 40% of work in 6 days. Then, find in how many days 60% of the same work will be completed by A & C working together, if A is working with 5% more efficiency.

A

4 days

B

6 days

C

5 days

D

3 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will follow the information given in the question and derive the required values systematically.

Step 1: Determine the Efficiency of A, B, and C

Let the efficiency of A be EA.

Since the efficiency of B is 40% more than A:
EB=EA+0.4EA=1.4EA

The efficiency of C is 150% of B:
EC=1.5EB=1.5×1.4EA=2.1EA

Step 2: Calculate the Total Work

B can complete 40% of the work in 6 days. Therefore, the total work can be calculated as follows:
If 40% of work is done in 6 days, then 100% of work will take 6 days0.4=15 days.

Step 3: Calculate the Total Work in Terms of Efficiency

Now, we can calculate the total work (W):
W=Total Time×Efficiency of B=15×EB
Substituting EB=1.4EA:
W=15×1.4EA=21EA

Step 4: Calculate the Efficiency of A with 5% Increase

A's efficiency is increased by 5%:
EA=EA+0.05EA=1.05EA

Step 5: Calculate the Combined Efficiency of A and C

Now, we can calculate the combined efficiency of A and C:
EA+C=EA+EC=1.05EA+2.1EA=3.15EA

Step 6: Calculate the Work to be Done

We need to find out how much work corresponds to 60% of the total work:
Required Work=0.6W=0.6×21EA=12.6EA

Step 7: Calculate the Time Taken by A and C to Complete 60% of Work

Using the formula for time:
Time=WorkEfficiency=12.6EA3.15EA
The EA cancels out:
Time=12.63.15=4 days

Conclusion

Therefore, A and C working together can complete 60% of the work in 4 days.

---

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    P is 20% more efficient than Q. If Q alone can finish a work in 10 days, then in how many days will P alone finish the work?

    A813
    B8.5
    C9
    D12
  • Question 2 - Select One

    A is 20% more efficient than B. If B alone can complete a piece of work in 12 days, then A alone can complete the same work in how many days?

    A10
    B12
    C14
    D15
  • Question 3 - Select One

    A is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?

    A10
    B12
    C14
    D16