Doubtnut Promotions Sticky

To complete a certain task, X is 30% more efficient than Y, and Z is 20% less efficient than Y. working together, they can complete the task in 44 days. Y and Z together worked for 70 days. The remaining work will completed by X alone in:

A

7 days

B

5 days

C

9 days

D

8 days

Text Solution
Verified by Experts

The correct Answer is:D

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    To complete a certain task, X is 40% more efficient than Y, and Z is 40% less efficient than Y. Working together, they can complete the task in 21 days. Y and Z together worked for 35 days. The remaining work will be completed by X alone in:
    किसी निश्चित कार्य को पूरा करने के लिए, X, Y की तुलना में 40% अधिक कार्य कुशल है तथा Z, Y से 40% कम कार्य कुशल है| एक साथ कार्य करते हुए, वे इस कार्य को 21 दिनों में पूरा कर सकते हैं | Y तथा Z ने 35 दिनों तक एक साथ कार्य किया | शेष कार्य A अकेला कितने दिनों में पूरा करेगा ?

    A4 days
    B8 days
    C5 days
    D6 days
  • Question 2 - Select One

    The efficiencies of A, B and C are in the ratio 5: 3: 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in:

    A30 days
    B32 days
    C36 days
    D40 days
  • Question 3 - Select One

    The efficiences of A , B and C are in ratio 5 : 3 : 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in :
    A, B और C की कार्य क्षमता 5 : 3 : 8 है| एक साथ कार्य करते हुए, वे किसी कार्य को 30 दिनों में कर सकते हैं | A और B ने 20 दिनों तक कार्य किया | शेष कार्य पूरा करने में C को अकेले कितने दिन लगेंगे?

    A40 days
    B36 days
    C30 days
    D32 days