Doubtnut Promotions Sticky

To complete a certain task, X is 40% more efficient than Y, and Z is 40% less efficient than Y. Working together, they can complete the task in 21 days. Y and Z together worked for 35 days. The remaining work will be completed by X alone in:
किसी निश्चित कार्य को पूरा करने के लिए, X, Y की तुलना में 40% अधिक कार्य कुशल है तथा Z, Y से 40% कम कार्य कुशल है| एक साथ कार्य करते हुए, वे इस कार्य को 21 दिनों में पूरा कर सकते हैं | Y तथा Z ने 35 दिनों तक एक साथ कार्य किया | शेष कार्य A अकेला कितने दिनों में पूरा करेगा ?

A

8 days

B

6 days

C

5 days

D

4 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will first determine the efficiencies of X, Y, and Z, calculate the total work, find out how much work Y and Z completed together, and finally calculate how long it will take X to finish the remaining work.

Step 1: Determine the efficiencies of X, Y, and Z
- Let the efficiency of Y be EY=5 units of work per day.
- Since X is 40% more efficient than Y:
EX=EY+0.4×EY=5+2=7 units/day
- Since Z is 40% less efficient than Y:
EZ=EY0.4×EY=52=3 units/day

Step 2: Calculate the total efficiency when X, Y, and Z work together
- The total efficiency when all three work together is:
Etotal=EX+EY+EZ=7+5+3=15 units/day

Step 3: Calculate the total work done
- They can complete the task in 21 days, so the total work W is:
W=Etotal×Time=15×21=315 units

Step 4: Calculate the work done by Y and Z in 35 days
- The combined efficiency of Y and Z is:
EY+Z=EY+EZ=5+3=8 units/day
- The work done by Y and Z in 35 days is:
WY+Z=EY+Z×35=8×35=280 units

Step 5: Calculate the remaining work
- The remaining work Wremaining is:
Wremaining=WWY+Z=315280=35 units

Step 6: Calculate how long it will take X to complete the remaining work
- Since X's efficiency is 7 units/day, the time T taken by X to complete the remaining work is:
T=WremainingEX=357=5 days

Final Answer
Thus, X will take 5 days to complete the remaining work.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A is 50% more efficient than B and C is 40% less efficient than B. Working together, they can complete a task in 10 days. In how many days, will A alone complete 150% of that task?
    A, B से अधिक कार्य कुशल है और C, B से 40% कम कार्य कुशल है | एक साथ कार्य करते हुए वे किसी कार्य को दस दिनों में पूरा कर सकते हैं | इस कार्य का 150% भाग पूरा करने में A को अकेले कितने दिन लगेंगे ?

    A33
    B35
    C28
    D31
  • Question 2 - Select One

    A is 50% more efficient than B and C is 40% less efficient than B. Working together, they can complete a task in 20 days. In how many days will C alone complete 30% of that task?
    A, B से 50% अधिक कार्य कुशल है तथा C, B से 40% कम कार्य कुशल है | एक साथ कार्य करते हुए, वे किसी कार्य को 20 दिनों में पूरा कर सकते हैं | C अकेले इस कार्य का 30% भाग कितने दिनों में पूरा करेगा ?

    A31
    B33
    C35
    D29
  • Question 3 - Select One

    To do a certain work, the ratio of the efficiencies of X and Y is 5:4. Working together, they can complete the same work in 10 days. Y alone starts the work and leaves after 5 days. The remaining work will be completed by X alone in :

    A14 days
    B12 days
    C15 days
    D10 days