A and B together can complete a work in 8 days and B and C together in 12 days. All of the three together can complete the work in 6 days. In how much time will A and C together complete the work?
8 days
10 days
12 days
20 days
The correct Answer is:A
To solve the problem step by step, we will first determine the work rates of A, B, and C based on the information provided.
Step 1: Determine the work done by A and B together.
A and B together can complete the work in 8 days. Therefore, the amount of work they can do in one day is:
Work rate of A + B=18 (work per day)
If we consider the total work to be 24 units, then:
Work done by A + B in 1 day=248=3 units
Step 2: Determine the work done by B and C together.
B and C together can complete the work in 12 days. Therefore, their work rate is:
Work rate of B + C=112 (work per day)
Thus, the work done by B and C in one day is:
Work done by B + C in 1 day=2412=2 units
Step 3: Determine the work done by A, B, and C together.
A, B, and C together can complete the work in 6 days. Therefore, their work rate is:
Work rate of A + B + C=16 (work per day)
Thus, the work done by A, B, and C in one day is:
Work done by A + B + C in 1 day=246=4 units
Step 4: Set up equations for the work rates.
From the above calculations, we have:
- A + B = 3 units/day
- B + C = 2 units/day
- A + B + C = 4 units/day
Step 5: Find the work done by A and C together.
To find the work done by A and C together, we can use the following relationship:
(A + C)=(A + B + C)−(B)
We can express B in terms of the other equations.
From A + B + C = 4 units and B + C = 2 units, we can find B:
B=(A+B+C)−(A+C)=4−(A+C)
Now, substituting the value of B from B + C:
B+C=2⟹(4−(A+C))+C=2
This simplifies to:
4−A=2⟹A=2 units
Step 6: Substitute to find C.
Now substituting A back into A + B = 3:
2+B=3⟹B=1 unit
Now substituting B into B + C = 2:
1+C=2⟹C=1 unit
Step 7: Calculate A + C.
Now we can find A + C:
A+C=2+1=3 units/day
Step 8: Calculate the time taken by A and C to complete the work.
To find the time taken by A and C together to complete the work:
Time=Total WorkWork Rate of A + C=243=8 days
Final Answer:
A and C together can complete the work in 8 days.
---
A and B together can complete the work in 8 days. Therefore, the amount of work they can do in one day is:
Work rate of A + B=18 (work per day)
If we consider the total work to be 24 units, then:
Work done by A + B in 1 day=248=3 units
B and C together can complete the work in 12 days. Therefore, their work rate is:
Work rate of B + C=112 (work per day)
Thus, the work done by B and C in one day is:
Work done by B + C in 1 day=2412=2 units
A, B, and C together can complete the work in 6 days. Therefore, their work rate is:
Work rate of A + B + C=16 (work per day)
Thus, the work done by A, B, and C in one day is:
Work done by A + B + C in 1 day=246=4 units
From the above calculations, we have:
- A + B = 3 units/day
- B + C = 2 units/day
- A + B + C = 4 units/day
To find the work done by A and C together, we can use the following relationship:
(A + C)=(A + B + C)−(B)
We can express B in terms of the other equations.
B=(A+B+C)−(A+C)=4−(A+C)
Now, substituting the value of B from B + C:
B+C=2⟹(4−(A+C))+C=2
This simplifies to:
4−A=2⟹A=2 units
Now substituting A back into A + B = 3:
2+B=3⟹B=1 unit
Now substituting B into B + C = 2:
1+C=2⟹C=1 unit
Now we can find A + C:
A+C=2+1=3 units/day
To find the time taken by A and C together to complete the work:
Time=Total WorkWork Rate of A + C=243=8 days
A and C together can complete the work in 8 days.
Topper's Solved these Questions
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-II45videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-III31videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI74videos
TIME AND DISTANCE
- BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF25videos
TRIGONOMETRY
Similar Questions
A and B together can complete a work in 12 days, B and C together can complete the same work in 8 days and A and C together can complete it in 16 days. In total, how many days do A, B and C together take to complete the same work? 3512 b. 3913 c. 7512 d. 7513 e. none of these
View SolutionTo complete a certain work, C working alone takes twice as long as A and B working together. A working alone takes 3 times as long as B and C working together. All the three together can complete the work in 5 days. How long would each take to complete th work individually?
View Solution
Knowledge Check
- Question 1 - Select One
A and B can together complete a work in 16 days. B and C can together complete the same work in 24 days and A, B and C together can complete the work in 12 days. Find time taken by A and C to complete the work together.
(a)12 days
(b)14 days
(c)16 days
(d)18 daysA12 daysB14 daysC16 daysD18 days - Question 2 - Select One
A and B together complete a work in 20 days, B and C together complete same work in 30 days, C and A together complete the same work 24 days, In how many days A, B and C together can complete the same work?
A8B16C12D15 - Question 3 - Select One
A and C together can complete a work in 120 days, C and E together can complete the same work in 80 days and A and E together can complete the same work in 160 days. In how many days A, C and E together can complete the same work?
A12013 daysB48013 daysC24013 daysD96013 days
A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B does the work only for half a day daily, then in how many days A and B together will complete the work? 110 days b. 11 days c. 15 days d. 20 days
View SolutionIf A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many day can A alone complete the work?
View SolutionIf A can complete work in 6 days, B can complete the work in 8 days and C can complete the same work in 12 days. In how much time A, B, and C can complete the work.
View SolutionA alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?
View SolutionIn how many days will B alone complete the work?
I. A and B together can complete the work in 8 days. II. B and C together can complete the work in 10 days.
III. A and C together can complete the work in 12 daysView Solution