The following table shows the time taken by four different persons (in hours) to do four different tasks. No tasks can be done at a time by two different persons.
If only two persons work on a particular day, then find the minimum time required to complete all the tasks, if the tasks can be done simultaneously?
10 h
12 h
11 h
9 h
The correct Answer is:D
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - DATA INTERPRETATIONEXERCISE - Previous Year Questions56videos
DATA INTERPRETATION
- BOOK - ADDA247CHAPTER - DATA INTERPRETATIONEXERCISE - Prelims Questions (Level-2)59videos
DATA INTERPRETATION
- BOOK - ADDA247CHAPTER - BOAT AND STREAM EXERCISE - Previous Year Question22videos
BOAT AND STREAM
- BOOK - ADDA247CHAPTER - DATA SUFFICIENCY EXERCISE - PREVIOUS YEAR QUESTIONS25videos
DATA SUFFICIENCY
Similar Questions
The number of different of different ways in which 8 persons can stand in a row so that between two particular persons A and B there are always two persons, is
View SolutionThe number of different of different ways in which 8 persons can stand in a row so that between two particular persons A and B there are always two persons, is
View Solution
Knowledge Check
- Question 1 - Select One
If 40 workers can complete a task in 24 days, then, find the time taken by 16 workers to complete twice the work.
A125 daysB122 daysC120 daysD116 days - Question 2 - Select One
12 persons can do a piece of work in 4 days. How many persons are required to complete 8 times the work in half the time?
A192B190C180D144 - Question 3 - Select One
The number of different ways in which 8 persons can stand in a row so that between two particular person A and B there are always two person, is
A60 (5!)B15(4!) × (5!)C4! × 5!DNone of these
12 persons can do a piece of work in 4 days. How many persons are required to complete 8 times the work in half the time? 144 b. 190 c. 180 d. 192
View SolutionIn how many ways four persons can be accommodated in 3 different chairs if each person can occupy only one chair.e
View SolutionThe following table gives the information regarding the number of persons employed to do a piece of work and time taken to complete the work:
Plot the line graph for this information.View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?
View SolutionIf two person P and Q together can complete a task is 12 days, P alone can complete it in 48 days then in how much time Q alone can complete this task?
View Solution