Doubtnut Promotions Sticky

The following table shows the time taken by four different persons (in hours) to do four different tasks. No tasks can be done at a time by two different persons.
The following table shows the time taken by four different persons (in hours) to do four different tasks. No tasks can be done at a time by two different persons.      If only two persons work on a particular day, then find the minimum time required to complete all the tasks, if the tasks can be done simultaneously?
If only two persons work on a particular day, then find the minimum time required to complete all the tasks, if the tasks can be done simultaneously?

A

10 h

B

12 h

C

11 h

D

9 h

Text Solution
Verified by Experts

The correct Answer is:D

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 40 workers can complete a task in 24 days, then, find the time taken by 16 workers to complete twice the work.

    A125 days
    B122 days
    C120 days
    D116 days
  • Question 2 - Select One

    12 persons can do a piece of work in 4 days. How many persons are required to complete 8 times the work in half the time?

    A192
    B190
    C180
    D144
  • Question 3 - Select One

    The number of different ways in which 8 persons can stand in a row so that between two particular person A and B there are always two person, is

    A60 (5!)
    B15(4!) × (5!)
    C4! × 5!
    DNone of these