A contractor undertook a contract to complete a part of a stadium in 9 months with a work force of 560 men. Later on it was required to complete the job in 7 months. Extra men employed by him is
160
150
100
120
The correct Answer is:A
Topper's Solved these Questions
- BOOK - MTG IIT JEE FOUNDATIONCHAPTER - DIRECT AND INVERSE PROPORTIONSEXERCISE - EXERCISE (MATCH THE FOLLOWING)2videos
DIRECT AND INVERSE PROPORTIONS
- BOOK - MTG IIT JEE FOUNDATIONCHAPTER - DIRECT AND INVERSE PROPORTIONSEXERCISE - EXERCISE (ASSERTION & REASON TYPE)5videos
DIRECT AND INVERSE PROPORTIONS
- BOOK - MTG IIT JEE FOUNDATIONCHAPTER - DIRECT AND INVERSE PROPORTIONSEXERCISE - EXERCISE(MULTIPLE CHOICE QUESTIONS) LEVEL-124videos
DIRECT AND INVERSE PROPORTIONS
- BOOK - MTG IIT JEE FOUNDATIONCHAPTER - DATA HANDLINGEXERCISE - Olympiad/HOTS Corner7videos
DATA HANDLING
- BOOK - MTG IIT JEE FOUNDATIONCHAPTER - EXPONENTS AND POWERSEXERCISE - Exercise (Integer/Numerical Value Type)10videos
EXPONENTS AND POWERS
Similar Questions
A contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?
View SolutionA contractor takes a contract to build a stadium with 430 men in 6 months. Later on he was asked to complete the work in 5 months. How many more men should he employ?
View Solution
Knowledge Check
- Question 1 - Select One
16 men finished one-third work in 6 days. The number of additional men are required to complete the job in next 6 days :
A10B8C16D32 - Question 2 - Select One
If 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?
A,21B20C24D22 - Question 3 - Select One
24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
A30B40C25D50
A work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?
View SolutionA work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?
View Solution24 men can complete a job in 20 days. The number of men required to complete the job in 16 days is :
View Solution24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
View SolutionA contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?
View Solution