Doubtnut Promotions Sticky

A contractor undertook a contract to complete a part of a stadium in 9 months with a work force of 560 men. Later on it was required to complete the job in 7 months. Extra men employed by him is

A

160

B

150

C

100

D

120

Text Solution
Verified by Experts

The correct Answer is:A

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    16 men finished one-third work in 6 days. The number of additional men are required to complete the job in next 6 days :

    A10
    B8
    C16
    D32
  • Question 2 - Select One

    If 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?

    A,21
    B20
    C24
    D22
  • Question 3 - Select One

    24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :

    A30
    B40
    C25
    D50