Doubtnut Promotions Sticky

A contractor takes a contract to build a stadium with 430 men in 6 months. Later on he was asked to complete the work in 5 months. How many more men should he employ?

Video Solution
|
Answer

Step by step video & image solution for A contractor takes a contract to build a stadium with 430 men in 6 months. Later on he was asked to complete the work in 5 months. How many more men should he employ? by Maths experts to help you in doubts & scoring excellent marks in Class 8 exams.

Updated on:21/07/2023

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?

    A100
    B60
    C75
    DNone of these
  • Question 2 - Select One

    A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?

    A70
    B75
    C80
    D85
  • Question 3 - Select One

    A contractor undertakes to make a mall in 60 days and he
    employs 30 men. After 30 days it is found that only one-
    third of the work is completed. How many extre men should
    he employ so that the work is completed on time?

    A20 men
    B25 men
    C30 men
    D40 men