150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on the third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was complete.
The correct Answer is:N/a
Let the work is completed in 'n' days.
No. of workers engaged on second day =150-4=146
No. of workers engaged of third day =150−2×4=142
Series formed from n terms : 150, 146, 142,….
Hera a=150,d=146−150=142−146=−4
∴ Sn=n2[2a+(n−1)d]
=n2[2×150+(n−1)(−4)]=152n−2n2
If 150 workers engaged then work completes in (n-8) days
∴ 150(n−8)=152−2n2
⇒ 2n2−2n−1200=0
⇒ n2−n−600=0
⇒ (n−25)(n+24)=0
⇒ n−25=0orn+24=0
⇒ n=25or n=−24
n=−24 is not possible.
Therefore, work is completed in 25 days.
Topper's Solved these Questions
Similar Questions
150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
View SolutionAbout 150 workers were engaged to finish a piece of work in a certain number of days. Four workers stopped working on the second day, four more workers stopped their work on the third day and so on. It took 8 more days to finish the work. Then the number of days in which the work was completed is 29 days b. 24 days c. 25 days d. none of these
View Solution
Knowledge Check
- Question 1 - Select One
150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
A24 daysB40 daysC17 daysD25 days - Question 2 - Select One
8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
A2B3C4D5 - Question 3 - Select One
30 workers can finish a work in 20 days. After how many days should 9 workers leave the job so that the work is completed in total 26 days :
A12B10C6Dnone of these
In a factory, 150 workers were engaged to finish a piece of work in a certain number of days. However, if 4 workers are dropped everyday, except the first day, it will take 8 more days to finish the work. Find the number of days in which the work was to be completed.
View Solution8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
View Solution8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finIsh the work. In how many days would the remaining work be completed?
View Solution100 workers finish a work in 20, days. How many workers are required to finish the work in 25 days ?
View Solution56 workers canfinish a piece of work in 14 days. If the work
is to be completed in 8 days, then how many extra workers
are required ?View Solution