Doubtnut Promotions Sticky

150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on the third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was complete.

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:N/a


Let the work is completed in 'n' days.
No. of workers engaged on second day =150-4=146
No. of workers engaged of third day =1502×4=142
Series formed from n terms : 150, 146, 142,….
Hera a=150,d=146150=142146=4
Sn=n2[2a+(n1)d]
=n2[2×150+(n1)(4)]=152n2n2
If 150 workers engaged then work completes in (n-8) days
150(n8)=1522n2
2n22n1200=0
n2n600=0
(n25)(n+24)=0
n25=0orn+24=0
n=25or n=24
n=24 is not possible.
Therefore, work is completed in 25 days.

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.

    A24 days
    B40 days
    C17 days
    D25 days
  • Question 2 - Select One

    8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?

    A2
    B3
    C4
    D5
  • Question 3 - Select One

    30 workers can finish a work in 20 days. After how many days should 9 workers leave the job so that the work is completed in total 26 days :

    A12
    B10
    C6
    Dnone of these