A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?
6
8
5
10
The correct Answer is:C
To solve the problem step by step, we will first determine the work done by A and B individually, then calculate the work they accomplish together, and finally find out how long A will take to finish the remaining work after B leaves.
Step 1: Determine the work done by A and B individually.
- A can complete the work in 15 days.
- B can complete the work in 10 days.
To find their work rates (efficiency), we can express the total work in terms of a common unit. Let's assume the total work is 30 units (the least common multiple of 15 and 10).
- Work done by A in one day = Total work / Days taken by A = 30 / 15 = 2 units/day
- Work done by B in one day = Total work / Days taken by B = 30 / 10 = 3 units/day
Step 2: Calculate the combined work done by A and B in 4 days.
When A and B work together, their combined work rate is:
- Combined work rate = Work done by A + Work done by B = 2 + 3 = 5 units/day
Now, we calculate the work done when they work together for 4 days:
- Work done in 4 days = Combined work rate × Number of days = 5 units/day × 4 days = 20 units
Step 3: Calculate the remaining work after A and B have worked together.
Total work = 30 units
Work completed by A and B together = 20 units
Remaining work = Total work - Work completed = 30 - 20 = 10 units
Step 4: Determine how long A will take to complete the remaining work alone.
Now, A will complete the remaining 10 units of work alone. We know A's work rate is 2 units/day.
To find the number of days A will take to complete the remaining work:
- Days taken by A = Remaining work / Work rate of A = 10 units / 2 units/day = 5 days
Final Answer:
A will take 5 days to complete the remaining work alone.
---
- B can complete the work in 10 days.
- Work done by B in one day = Total work / Days taken by B = 30 / 10 = 3 units/day
- Combined work rate = Work done by A + Work done by B = 2 + 3 = 5 units/day
- Work done in 4 days = Combined work rate × Number of days = 5 units/day × 4 days = 20 units
Work completed by A and B together = 20 units
- Days taken by A = Remaining work / Work rate of A = 10 units / 2 units/day = 5 days
A will take 5 days to complete the remaining work alone.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 219videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 321videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - TEST YOUR CONCEPTS50videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - BANKING AND COMPUTINGEXERCISE - Level 36videos
BANKING AND COMPUTING
Similar Questions
A and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?
View SolutionA and B can complete a work in 12 days and 15 days respectively. They started the work together. If after 4 days A leaves the job, then in how many days B will complete the remaining work?
View Solution
Knowledge Check
- Question 1 - Select One
Rakesh and Siva can do a piece of work in 15 days and 18 days respectively. They work together for 5 days and then Rakesh leaves. In how many days will Siva alone finish the remaining work?
A5B6C8D7 - Question 2 - Select One
Rakesh and Siva can do a piece of work in 15 days and 18 days respectively. They work together for 5 days and then Rakesh leaves. In how many days will Siva alone finish the remaining work?
A5B6C8D7 - Question 3 - Select One
Rakesh and Siva can do a piece of work in 15 days and 18 days respectively. They work together for 5 days and then Rakesh leaves. In how many days will Siva alone finish the remaining work?
A5B6C8D7
A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in:
View SolutionRam and Mohan can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days Mohan had to leave and Ram alone completed the remaining work The whole work was completed in:
View SolutionA, B and C can complete a piece of work in 10, 20 and 60 days respectively. Working together they can complete the same work in how many days?
View SolutionA, B and C can complete a piece of work in 5, 20 and 60 days respectively. Working together, they can complete the same work in how many days ?
A, B और C किसी कार्य को क्रमशः 5, 20 और 60 दिनों में पूरा कर सकते हैं | एक साथ कार्य करते हुए, वे इस कार्य को कितने दिनों में पूरा करेंगे ?View SolutionA, B and c can complete a piece of work in 10, 20 and 60 days respectively. Working together can complete the same work in how many days?
View Solution