A and B can complete a piece of work in 4 days and 8 days, respctively. They work on alternate days and A starts the work. In how work in may days will the work be completed
3
4
5
6
The correct Answer is:C
To solve the problem step by step, we will determine how much work A and B can do in one day, and then calculate how many days it will take for them to complete the work when they work alternately.
1. Determine the work done by A in one day:
- A can complete the work in 4 days. Therefore, the work done by A in one day is:
Work done by A in one day=14
2. Determine the work done by B in one day:
- B can complete the work in 8 days. Therefore, the work done by B in one day is:
Work done by B in one day=18
3. Calculate the total work done in 2 days (one cycle of A and B working):
- On the first day, A works and completes 14 of the work.
- On the second day, B works and completes 18 of the work.
- Therefore, the total work done in 2 days is:
Total work in 2 days=14+18
- To add these fractions, we need a common denominator:
14=28(converting to a common denominator)
- Now, add the fractions:
Total work in 2 days=28+18=38
4. Determine how many cycles are needed to complete the work:
- Since 38 of the work is done in 2 days, we need to find out how many such cycles are needed to complete the entire work (1 unit of work).
- Let n be the number of cycles (2 days each) needed:
n⋅38≥1
- Solving for n:
n≥83≈2.67
- This means we need 3 cycles (since we can't have a fraction of a cycle).
5. Calculate the work done after 3 cycles (6 days):
- In 6 days (3 cycles), the work done will be:
3⋅38=98
- This means the work is complete after 6 days, and we have 18 of the work remaining.
6. Determine how much more time is needed to complete the remaining work:
- On the 7th day, A works again and completes 14 of the work. Since only 18 of the work is left, A will complete the remaining work on the 7th day.
- Thus, the total time taken to complete the work is:
6 days+1 day=7 days
Conclusion:
The total time taken to complete the work is 7 days.
- A can complete the work in 4 days. Therefore, the work done by A in one day is:
Work done by A in one day=14
- B can complete the work in 8 days. Therefore, the work done by B in one day is:
Work done by B in one day=18
- On the first day, A works and completes 14 of the work.
- On the second day, B works and completes 18 of the work.
- Therefore, the total work done in 2 days is:
Total work in 2 days=14+18
- To add these fractions, we need a common denominator:
14=28(converting to a common denominator)
- Now, add the fractions:
Total work in 2 days=28+18=38
- Since 38 of the work is done in 2 days, we need to find out how many such cycles are needed to complete the entire work (1 unit of work).
- Let n be the number of cycles (2 days each) needed:
n⋅38≥1
- Solving for n:
n≥83≈2.67
- This means we need 3 cycles (since we can't have a fraction of a cycle).
- In 6 days (3 cycles), the work done will be:
3⋅38=98
- This means the work is complete after 6 days, and we have 18 of the work remaining.
- On the 7th day, A works again and completes 14 of the work. Since only 18 of the work is left, A will complete the remaining work on the 7th day.
- Thus, the total time taken to complete the work is:
6 days+1 day=7 days
The total time taken to complete the work is 7 days.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 219videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 321videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - TEST YOUR CONCEPTS50videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - BANKING AND COMPUTINGEXERCISE - Level 36videos
BANKING AND COMPUTING
Similar Questions
A and B can do a piece of work in 6 days and 9 days respectively, they work on alternative days starting with A on the first day. In how many days will the work be completed ?
View SolutionA and B can do a piece of work in 6 days and 9 days respectively, they work on alternative days starting with A on the first day. In how many days will the work be completed ?
View Solution
Knowledge Check
- Question 1 - Select One
Fatima and Zahira can do a piece of work in 12 days and 15 days respectively. If they work for alternate day and Fatima starts the work first, then in how many days the work will be completed?
A1215B1314C1315D15 - Question 2 - Select One
Fatima and Zahira can do a piece of work in 12 days and 15 days respectively. If they work for alternate day and Fatima starts the work first, then in how many days the work will be completed?
A1215B1314C1315D15 - Question 3 - Select One
A and B working separately can do a piece of work in 10 days and 15 days respectively. If they work on alternate days beginning with A, in how many days will the work be complete?
A18 daysB13 daysC12 daysD6 days
A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
View SolutionA and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
View SolutionA and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
View SolutionA and B working separately can do a piece of work in 10 days and 15 days respectively. If they work on alternate days beginning with A, in how many days will the work be complete?
View SolutionA and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?
View Solution