Doubtnut Promotions Sticky

A and B can complete a piece of work in 4 days and 8 days, respctively. They work on alternate days and A starts the work. In how work in may days will the work be completed

A

3

B

4

C

5

D

6

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will determine how much work A and B can do in one day, and then calculate how many days it will take for them to complete the work when they work alternately.

1. Determine the work done by A in one day:
- A can complete the work in 4 days. Therefore, the work done by A in one day is:
Work done by A in one day=14

2. Determine the work done by B in one day:
- B can complete the work in 8 days. Therefore, the work done by B in one day is:
Work done by B in one day=18

3. Calculate the total work done in 2 days (one cycle of A and B working):
- On the first day, A works and completes 14 of the work.
- On the second day, B works and completes 18 of the work.
- Therefore, the total work done in 2 days is:
Total work in 2 days=14+18
- To add these fractions, we need a common denominator:
14=28(converting to a common denominator)
- Now, add the fractions:
Total work in 2 days=28+18=38

4. Determine how many cycles are needed to complete the work:
- Since 38 of the work is done in 2 days, we need to find out how many such cycles are needed to complete the entire work (1 unit of work).
- Let n be the number of cycles (2 days each) needed:
n381
- Solving for n:
n832.67
- This means we need 3 cycles (since we can't have a fraction of a cycle).

5. Calculate the work done after 3 cycles (6 days):
- In 6 days (3 cycles), the work done will be:
338=98
- This means the work is complete after 6 days, and we have 18 of the work remaining.

6. Determine how much more time is needed to complete the remaining work:
- On the 7th day, A works again and completes 14 of the work. Since only 18 of the work is left, A will complete the remaining work on the 7th day.
- Thus, the total time taken to complete the work is:
6 days+1 day=7 days

Conclusion:
The total time taken to complete the work is 7 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Fatima and Zahira can do a piece of work in 12 days and 15 days respectively. If they work for alternate day and Fatima starts the work first, then in how many days the work will be completed?

    A1215
    B1314
    C1315
    D15
  • Question 2 - Select One

    Fatima and Zahira can do a piece of work in 12 days and 15 days respectively. If they work for alternate day and Fatima starts the work first, then in how many days the work will be completed?

    A1215
    B1314
    C1315
    D15
  • Question 3 - Select One

    A and B working separately can do a piece of work in 10 days and 15 days respectively. If they work on alternate days beginning with A, in how many days will the work be complete?

    A18 days
    B13 days
    C12 days
    D6 days