Doubtnut Promotions Sticky

A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?

A

14

B

12

C

18

D

10

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will determine how long it takes for A, B, and C to complete the work together and how long it takes for B to finish the remaining work after A and C leave.

Step 1: Determine the work done by A, B, and C in one day.

- A can complete the work in 25 days. Therefore, the work done by A in one day is:
Work done by A in one day=125 of the work

- B can complete the work in 30 days. Therefore, the work done by B in one day is:
Work done by B in one day=130 of the work

- C can complete the work in 50 days. Therefore, the work done by C in one day is:
Work done by C in one day=150 of the work

Step 2: Calculate the total work done by A, B, and C in one day.

To find the total work done by A, B, and C together in one day, we add their individual contributions:
Total work done in one day=125+130+150

To add these fractions, we need to find a common denominator. The LCM of 25, 30, and 50 is 150.

Now, convert each fraction:
125=6150,130=5150,150=3150

Adding these together:
Total work done in one day=6+5+3150=14150=775

Step 3: Determine how many days they worked together before A and C left.

Let x be the total number of days they worked together. Since A and C left 2 days before the work was completed, they worked together for x2 days.

The total work done by A, B, and C in x2 days is:
Work done=(775)(x2)

Step 4: Calculate the remaining work after A and C leave.

After A and C leave, only B is left to complete the work. The work done by B in one day is 130.

The total work done by B in 2 days is:
Work done by B in 2 days=2×130=230=115

Step 5: Set up the equation for total work.

The total work is 1 (the whole job), so we can set up the equation:
(775)(x2)+115=1

Step 6: Solve the equation.

First, convert 115 to have a common denominator of 75:
115=575

Now substitute back into the equation:
(775)(x2)+575=1

Multiply through by 75 to eliminate the denominator:
7(x2)+5=75
7x14+5=75
7x9=75
7x=84
x=12

Step 7: Conclusion

The total time taken to complete the work is 12 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?

    A14
    B12
    C18
    D10
  • Question 2 - Select One

    A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B1025
    C10730
    Dnone of these
  • Question 3 - Select One

    A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B10215
    C10730
    Dnone of these