A piece of work can be done by 16 man in 8 days working 12 hours a day. How many men ar needed to complete another work,which is three times the first one, in 24n days working 8 hourse, a day?
Using the formula, M1D1H1W1=M2D2H2W2
Let W1=xandW2=3x
M1=16,H1=12,D1=8
H2=8,D2=24
∴16×8×12x=M2×24×83x
⇒M2=24
∴ Requrired numbrer of men is 34
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - TEST YOUR CONCEPTS50videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 130videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - BANKING AND COMPUTINGEXERCISE - Level 36videos
BANKING AND COMPUTING
Similar Questions
A piece of work can be done by 16 men in 8 days working 12 hours a day. How many men are needed to complete another work, which is three times the first one, in 24 days working 8 hours a days ?
View SolutionA piece of work can be done by 16 men in 8 days working 12 hours a day. How many men are needed to complete another work, which is three times the first one, in 24 days working 8 hours a days ?
View Solution
Knowledge Check
- Question 1 - Select One
A piece of work in be done by 64 men in 17 days working for 9 hourse per day. In how many days can 34 men do a piece of work 83 times of the previous one one on working 8 hore per day ?
A92B98C96D94 - Question 2 - Select One
12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men are engaged in the same work ?
A28B36C48D52 - Question 3 - Select One
If 90 men can do a certain job in 16 days, working 12 hours day, then the part of that work which can be completed by 70 men in 24 days wokring 8 hours/day is.
A13B23C79D58
If 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View Solution12 men can complete a work in 30 days by working 9 hours a day. What is the number of men required to complete 10 times of this work in 24 days by working 5 hours a day ?
View Solution15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
View Solution