Doubtnut Promotions Sticky

A piece of work can be done by 16 man in 8 days working 12 hours a day. How many men ar needed to complete another work,which is three times the first one, in 24n days working 8 hourse, a day?

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

Using the formula, M1D1H1W1=M2D2H2W2
Let W1=xandW2=3x
M1=16,H1=12,D1=8
H2=8,D2=24
16×8×12x=M2×24×83x
M2=24
Requrired numbrer of men is 34

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A piece of work in be done by 64 men in 17 days working for 9 hourse per day. In how many days can 34 men do a piece of work 83 times of the previous one one on working 8 hore per day ?

    A92
    B98
    C96
    D94
  • Question 2 - Select One

    12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men are engaged in the same work ?

    A28
    B36
    C48
    D52
  • Question 3 - Select One

    If 90 men can do a certain job in 16 days, working 12 hours day, then the part of that work which can be completed by 70 men in 24 days wokring 8 hours/day is.

    A13
    B23
    C79
    D58