Doubtnut Promotions Sticky

A printing company prints two types of magazines _A and 8. The company earns '10 and '15 on each magazine A and 8 respectively. These are processed on three machines I, II and Ill and total time in hours available per week on each machine is as follows.
A printing company prints two types of magazines A and 8. The company earns '10 and '15 on each magazine A and 8 respectively. These are processed on three machines I, II and Ill and total time in hours available per week on each machine is as follows.      The number of constraints is
The number of constraints is

A

3

B

4

C

5

D

6

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:C


Constriants are 2x+3y36,5x+2y50,2x=6y60,x0,y0
The number of constraints are 5.

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A printing company prints two types of magzines A and B. The company earns Rs. 20 and Rs. 30 on each copy of magazines A and B respectively. The magazine A requires 2 hours on machine I, 4 hours on Machine II and 2 hours machine III. Magazine B requires 3 hours on machine I, 5 hours on machine II and 3 hours on machine III. Machines I,II, III are available for 35, 50 and 70 hours per week respectively. Formulate the LPP to determine weekly production of magazines A and B, so that the total profit is maximum

    AMaximize z=20x+3y subject to 2x+3y35,4x+5y50,2x+3y70,x0,y0
    BMaximize z=20x+3y subject to 2x+3y35,4x+5y50,2x+3y70,x0,y0
    CMaximize z=20x+3y subject to 2x+3y35,4x+5y50,2x+3y70,x0,y0
    DMaximize z=20x+3y subject to 2x+3y35,4x+5y50,2x+3y70,x0,y0
  • Question 2 - Select One

    In a press, there are three types of printing machines, P, Q and R. Machine P can print 10,000 pages in 8 hours, machine Q can finish the same task in 10 hours and machine R can finish the same task in 15 hours. All the three machines start the work at 9:00 a. m. Machine P breaks down at 11:00 a.m. and machines Q and R finish the task. The approximate time of completion of the job is :

    A2:05 p.m.
    B2:30 p.m.
    C1:50 p.m.
    D1:30 p.m.
  • Question 3 - Select One

    A tailor stiches trousers and shirts and each piece is completed by two machine I and II. To complete each trousers, machines I and II must work 3/2 hours and 2 hours respectively, and to complete each shirt, machines I and II must work 2 hours and 1 hours respectively Machine I may not operate for more than 12 hours ped day and machine II not more than 11 hours per day. If the profit on each trouser and each shirt is Rs. 150 and Rs. 100 repectively, then the maximum profit is _______

    ARs. 900
    BRs. 500
    CRs. 375
    DRs. 600