Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
The correct Answer is:16
To solve the problem step by step, we can use the concept of work done, which is calculated as the product of the number of men, the number of days, and the number of hours worked per day.
Step 1: Calculate the total work done by 15 men in 10 days working 8 hours per day.
Total work (W1) = Number of men (M1) × Number of days (D1) × Hours per day (T1)
Given:
- M1 = 15 men
- D1 = 10 days
- T1 = 8 hours/day
W1=15×10×8=1200 man-hours
Step 2: Determine the total work required for double the work.
Since we need to complete double the work, we have:
W2=2×W1=2×1200=2400 man-hours
Step 3: Set up the equation for the new scenario.
We need to find out how many men (M2) are required to complete this work in 25 days working 6 hours per day.
Total work (W2) can also be expressed as:
W2=M2×D2×T2
Where:
- D2 = 25 days
- T2 = 6 hours/day
Step 4: Substitute the values into the equation.
2400=M2×25×6
Step 5: Solve for M2.
First, calculate 25×6:
25×6=150
Now, substitute this back into the equation:
2400=M2×150
To find M2, divide both sides by 150:
M2=2400150=16
Conclusion:
Therefore, 16 men are required to complete double the work in 25 days working 6 hours per day.
---
- M1 = 15 men
- D1 = 10 days
- T1 = 8 hours/day
- D2 = 25 days
- T2 = 6 hours/day
Topper's Solved these Questions
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-1)
33 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-2)
20 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - Short Answer Type Questions
15 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
Similar Questions
Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionIf 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?
View Solution
Knowledge Check
7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?
A28B21C14D77 men can complete a plece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?
A28B21C14D718 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
A25B15C20D9
12 men can complete a work in 30 days by working 9 hours a day. What is the number of men required to complete 10 times of this work in 24 days by working 5 hours a day ?
View Solution18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
View Solution7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work
View Solution30 persons can complete a work in 10 days. If they work 4 hours per day, then in how many days 45 persons can complete double the work if they work 8 hours per day? It is known that 2 persons of first type can do the same work in 2 hours that can be completed by 4 persons of 2nd type in 1 hour.
View SolutionIf 20 men take 15 days to complete a certain amount of work working at 10 hours per day, then how many more men are required to complete twice the previous work in 10 days working at 12 hours a day?
View Solution