Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:16


To solve the problem step by step, we can use the concept of work done, which is calculated as the product of the number of men, the number of days, and the number of hours worked per day.

Step 1: Calculate the total work done by 15 men in 10 days working 8 hours per day.

Total work (W1) = Number of men (M1) × Number of days (D1) × Hours per day (T1)

Given:
- M1 = 15 men
- D1 = 10 days
- T1 = 8 hours/day

W1=15×10×8=1200 man-hours

Step 2: Determine the total work required for double the work.

Since we need to complete double the work, we have:

W2=2×W1=2×1200=2400 man-hours

Step 3: Set up the equation for the new scenario.

We need to find out how many men (M2) are required to complete this work in 25 days working 6 hours per day.

Total work (W2) can also be expressed as:

W2=M2×D2×T2

Where:
- D2 = 25 days
- T2 = 6 hours/day

Step 4: Substitute the values into the equation.

2400=M2×25×6

Step 5: Solve for M2.

First, calculate 25×6:

25×6=150

Now, substitute this back into the equation:

2400=M2×150

To find M2, divide both sides by 150:

M2=2400150=16

Conclusion:

Therefore, 16 men are required to complete double the work in 25 days working 6 hours per day.

---

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?

    A28
    B21
    C14
    D7
  • 7 men can complete a plece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?

    A28
    B21
    C14
    D7
  • 18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?

    A25
    B15
    C20
    D9