Doubtnut Promotions Sticky

P and Q can complete a certain in 28 days and 56 days, respectively. P works for 7 days, and then Q joins P . In how many more days, can they complete the work ?

A

7

B

14

C

21

D

28

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will first determine the work done by P and Q, and then calculate how much work is left after P works alone for 7 days. Finally, we will find out how many more days they will take to complete the remaining work together.

Step 1: Determine the work done by P and Q in one day.

- P can complete the work in 28 days, so the work done by P in one day is:
Work done by P in one day=128

- Q can complete the work in 56 days, so the work done by Q in one day is:
Work done by Q in one day=156

Step 2: Calculate the total work done by P in 7 days.

- In 7 days, P will complete:
Work done by P in 7 days=7×128=728=14

Step 3: Calculate the remaining work after P has worked for 7 days.

- The total work can be considered as 1 unit (the whole work). Therefore, the remaining work after P has worked for 7 days is:
Remaining work=114=34

Step 4: Calculate the combined work done by P and Q in one day.

- The combined work done by P and Q in one day is:
Combined work=128+156

To add these fractions, we need a common denominator. The least common multiple of 28 and 56 is 56.

128=256

Therefore,
Combined work=256+156=356

Step 5: Calculate how many days P and Q will take to complete the remaining work.

- To find out how many days it will take for P and Q to complete the remaining 34 of the work, we set up the equation:
Days required=Remaining workCombined work per day=34356=34×563=14

Final Answer:
- Therefore, P and Q will take 14 more days to complete the work after Q joins P.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B separately can complete a work in 6 days and 3 days respectively. If they work together. Then in how many days will they complete the work ?

    A4 days
    B3 days
    C2 days
    D5 days
  • Question 2 - Select One

    P, Q and R can complete a work in 30 days, 15 days and 20 days respectively. P works on first day, then Q works on second day and then R works on third day and so on. In how many days the work will be completed?

    A20 days
    B21 days
    C22 days
    D19 days
  • Question 3 - Select One

    A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?

    A4
    B15
    C154
    D16