P and Q can complete a certain in 28 days and 56 days, respectively. P works for 7 days, and then Q joins P . In how many more days, can they complete the work ?
7
14
21
28
The correct Answer is:B
To solve the problem step by step, we will first determine the work done by P and Q, and then calculate how much work is left after P works alone for 7 days. Finally, we will find out how many more days they will take to complete the remaining work together.
Step 1: Determine the work done by P and Q in one day.
- P can complete the work in 28 days, so the work done by P in one day is:
Work done by P in one day=128
- Q can complete the work in 56 days, so the work done by Q in one day is:
Work done by Q in one day=156
Step 2: Calculate the total work done by P in 7 days.
- In 7 days, P will complete:
Work done by P in 7 days=7×128=728=14
Step 3: Calculate the remaining work after P has worked for 7 days.
- The total work can be considered as 1 unit (the whole work). Therefore, the remaining work after P has worked for 7 days is:
Remaining work=1−14=34
Step 4: Calculate the combined work done by P and Q in one day.
- The combined work done by P and Q in one day is:
Combined work=128+156
To add these fractions, we need a common denominator. The least common multiple of 28 and 56 is 56.
128=256
Therefore,
Combined work=256+156=356
Step 5: Calculate how many days P and Q will take to complete the remaining work.
- To find out how many days it will take for P and Q to complete the remaining 34 of the work, we set up the equation:
Days required=Remaining workCombined work per day=34356=34×563=14
Final Answer:
- Therefore, P and Q will take 14 more days to complete the work after Q joins P.
---
Work done by P in one day=128
Work done by Q in one day=156
Work done by P in 7 days=7×128=728=14
Remaining work=1−14=34
Combined work=128+156
To add these fractions, we need a common denominator. The least common multiple of 28 and 56 is 56.
128=256
Therefore,
Combined work=256+156=356
Days required=Remaining workCombined work per day=34356=34×563=14
- Therefore, P and Q will take 14 more days to complete the work after Q joins P.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 219videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 321videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - TEST YOUR CONCEPTS50videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - BANKING AND COMPUTINGEXERCISE - Level 36videos
BANKING AND COMPUTING
Similar Questions
Knowledge Check
- Question 1 - Select One
A and B separately can complete a work in 6 days and 3 days respectively. If they work together. Then in how many days will they complete the work ?
A4 daysB3 daysC2 daysD5 days - Question 2 - Select One
P, Q and R can complete a work in 30 days, 15 days and 20 days respectively. P works on first day, then Q works on second day and then R works on third day and so on. In how many days the work will be completed?
A20 daysB21 daysC22 daysD19 days - Question 3 - Select One
A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16
A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
View SolutionA and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
View SolutionA and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
View SolutionP,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).
View SolutionP,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).
View Solution