After working for 8 days Hari Ram finds that only 1/3 rd of the work has been done. He employs Satya who is 60% as efficient as Hari Ram. How many days more would Satya take to complete the work ?
1 24 1/2 days
2 25 3/2 days
3 24 2/3 days
4 26 2/3 days
Answer : 4. "26 2/3 days" Explanation :Answer: D) 26 2/3 days Explanation: 1
Related Solutions
After working for 8 days, Anil finds that only of the work has been done. He employs Rakesh who is 60% efficient as Anil. How many more days will Anil take to complete the job?
View SolutionAfter working for 8 days, Anil finds that only of the work has been done. He employs Rakesh who is 60% efficient as Anil. How many more days will Anil take to complete the job?
View SolutionRama and Hari together can do a work in 15 days. Rama is twice as efficient as Hari. In how many days will Hari alone do the same work?
View SolutionRam and Hari can cut 12 kg of kernels in 2 days. After 5 days Hari left the work and left. It took 8 more days for Ram to cut the remaining kernel. If total 58 kg. If the kernel was cut, Hari got 10 kg. How long will it take to cut the kernel?
View SolutionRam completes a work in 16 days, Lakshmana takes 20 days to complete the same work. They work together for 4 days and then Ram leaves. And in how many days will Laxman complete the work?
View SolutionMohit is five times more efficient as Rohit. If Mohit can complete a piece of work in 28 days less than Rohit, then in how many days can Rohit alone complete the same work?
मोहित रोहित से पांच गुना अधिक कार्य कुशल है। अगर मोहित किसी कार्य को पूरा करने में रोहित की तुलना में 28 दिन कम का समय लेता है,तो रोहित अकेले इस कार्य को कितने दिन में पूरा करेगा ?View SolutionRama and Hari together can complete a piece of work in 15 days. Rama works twice as fast as Hari, then in how many days can Hari alone complete the work?
View SolutionNandu can do a piece of work in 15 days. Hari can do the same work in 10 days. Nandu stops this work after 9 days. In how many days will Hari do the remaining work?
View SolutionRahul is twice efficient as Ram. If both of them can complete the work in 12 days. Then find the number of days Rahul would take to complete the work above.
View SolutionA piece of work can be done by Ram and Shyam in 12 days, by Shyam and Harlin 15 days and by Harlin and Ram in 20 days. Ram alone will complete the work in
View SolutionA contractor took a contract to complete a work in 40 days. He initially employed 100 men and after 35 days, he employed 100 more and completed the work on time. If that extra person had not employed then after how many days would the work have been finished after the right time?
View SolutionA contractor takes a contract to get a work done in 38 days. Employing 30 men, he works for 25 days. Later, by employing 5 more people, he gets the work completed in one day, if 5 more people had not come, then by how many days would the work be finished late?
View SolutionCan complete a work in 12 days. B is 60% more efficient than A. In how many days will B take to complete the same work?
View SolutionRam and Shyam work on a job together for four days and complete 60% of it am takes leave then and Shyam works for eight more days to complete the job How long would Ram take to complete the entire job alone? (a) 6 days (b) 8days (c) 10days 11days
View SolutionRam and Shyam together can do a work in 8days. Both of them began to work. After 3 days Ram fell ill, Shyam completed the remaining work in 15 days. In how many days can Ram complete the whole work?
View SolutionRam and Mohan can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days Mohan had to leave and Ram alone completed the remaining work The whole work was completed in:
View SolutionRam and Shyam can complete a task in days and 15 days, respectively. The work together for 4 days, and then Ram leaves. In how many days after Ram leaves, will Shayam complete the remaining task alone?
View SolutionA can finish a work in 12 days. B is 60% more efficient than A. How many days will B take to complete the same work ?
View SolutionRam can do a work in 15 days, while Ram and Shiva work together they can complete the work in 10 days, in how many days Shiva can alone do the same work?
View SolutionA is 1.5 times as efficient as B, so he takes 8 days less than B to complete a piece of work. A and B work on alternate days and A does the work on the first day, then in how many days will the work be completed?
View Solution