After working for 8 days Arun finds that only 13rd of the work has been done. He employs Akhil who is 60% as efficient as Arun. How many days more would Akhil take to complete the work?
1 24.5 days
2 26.6 days
3 25 days
4 20 days
Answer : 2. "26.6 days" Explanation :Answer: B) 26.6 days Explanation: Arun
Related Solutions
After working for 8 days, Anil finds that only of the work has been done. He employs Rakesh who is 60% efficient as Anil. How many more days will Anil take to complete the job?
View SolutionAfter working for 8 days, Anil finds that only of the work has been done. He employs Rakesh who is 60% efficient as Anil. How many more days will Anil take to complete the job?
View SolutionArun and Satyam can complete a work individually in ,12 working days and 15 working days respectively with their full efficiencies. Arun does work only on Monday, Wednesday and Friday while Satyam does the work on Tuesday, Thursday and Saturday. Sunday is always off. But Arun and Satyam both works with half of their efficiencies on Friday and Saturday respectively. If Arun started the work on 1st January which falls on Monday followed by Satyam on the next day and so on (i.e., they work collectively in alternate days), then on which day work will be completed?
View SolutionArun and Satyam can complete a work individually in ,12 working days and 15 working days respectively with their full efficiencies. Arun does work only on Monday, Wednesday and Friday while Satyam does the work on Tuesday, Thursday and Saturday. Sunday is always off. But Arun and Satyam both works with half of their efficiencies on Friday and Saturday respectively. If Arun started the work on 1st January which falls on Monday followed by Satyam on the next day and so on (i.e., they work collectively in alternate days), then on which day work will be completed?
View SolutionA contractor took a contract to complete a work in 40 days. He initially employed 100 men and after 35 days, he employed 100 more and completed the work on time. If that extra person had not employed then after how many days would the work have been finished after the right time?
View SolutionA contractor takes a contract to get a work done in 38 days. Employing 30 men, he works for 25 days. Later, by employing 5 more people, he gets the work completed in one day, if 5 more people had not come, then by how many days would the work be finished late?
View SolutionCan complete a work in 12 days. B is 60% more efficient than A. In how many days will B take to complete the same work?
View SolutionA can finish a work in 12 days. B is 60% more efficient than A. How many days will B take to complete the same work ?
View SolutionA is 1.5 times as efficient as B, so he takes 8 days less than B to complete a piece of work. A and B work on alternate days and A does the work on the first day, then in how many days will the work be completed?
View Solution14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ?
View Solution35 men are employed to complete a work in 60 days. After 32 days it is found that only (2/5) Only part has been completed. How many persons will be required to complete the remaining work in the said period?
View SolutionArun and Amit can do a piece of work in 9 days and 12 days respectively . If they work for alternate days and Amit starts the work first , then in how many days 35/36 parts of whole work will be completed ?
View Solutionएक बिल्डर ने एक फार्महाउस 20 दिन में पूरा कराने का निर्णय लिया। आरंभ में उसने 40 व्यक्ति काम पर लगाये तथा 10 दिन बाद 20 व्यक्ति और काम पर लगाये और कार्य समय से पूरा हो गया। यदि वह अतिरिक्त व्यक्तियों को काम पर नहीं लगाता तो काम निश्चित समय से कितने दिन बाद पूरा होता?
View Solution24 women can complete a work in 45 days. If 18 women are employed, then in how many days the work would be completed?
View Solution24 women can complete a work in 45 days. If 18 women are employed, then in how many days the work would be completed?
View SolutionA किसी काम को 18 दिन में कर सकते है उसने 12 दिन काम किया और शेष काम B ने 8 दिन में पूरा किया B अकेले पुरे काम को कितने दिन में पूरा कर सकता था ?
View SolutionThe ratio of work efficiency of A & B is 2:5 . If A can complete a work in 10 days. In how many days the work can be completed by B and when they work together , in how many days the work would be completed ?
View SolutionA contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?
View Solutionएक बिल्डर ने एक फार्महाउस 45 दिन में बनाने का निर्णय लिया। आरंभ में उसने 150 व्यक्ति काम पर लगाये तथा 30 दिन बाद 120 व्यक्ति और काम पर लगाये और कार्य समय से पूरा हो गया। यदि वह अतिरिक्त व्यक्तियों को काम पर नहीं लगाता तो काम निश्चित समय से कितने दिन बाद पूरा होता ?
View SolutionA contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
View Solution