Seven men can complete a work in 12 days. They started the work and after 5 days two men left. In how many days will the work be completed by the remaining men?
1 5
2 6
3 7
4 None of these
Answer : 4. "None of these"
Related Solutions
12 men can do a piece of work in 90 days. After 30 days from the start of the work 2 men left the work and 8 men joined. In how many days will it take to complete the remaining work?
View Solution12 men can complete a work within 9 days. After 3 days they started the work, 6 men joined them to replace 2 men. How many days will they take to complete the remaining work?
View Solution15 men can complete a work in 24 days and 12 children in 60 days. 10 men started the work and after 12 days 12 children joined the work. In how many days will the remaining work be finished?
View Solution15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
View SolutionIf 10 men can complete a work in 12 days . In how many days can 18 men complete the same work ?
View Solution15 men can complete a work in 12 days they start the work together . In how many days the total work will be finished when. After 4 days 5 men left the work .
View Solution16 महिलाएं किसी काम को 12 दिनों में पूरा कर सकती है जबकि उसी काम को 12 पुरुष 8 दिनों में पूरा कर सकते है 16 पुरुष काम करना शुरू करते है और 3 दिन के बाद 10 पुरुष काम छोड़ देते है उसकी जगह 4 महिलाएं आ जाती है तो शेष काम कितने दिनों में पूरा होगा ?
View SolutionA work which 12 men can complete in 8 days can be completed by 16 women in 12 days. 16 men started working and after 3 days 10 men left and 4 women joined. In how many days will it take to complete the remaining work?
View Solution14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View Solution12 आदमी किसी कार्य को 90 दिनों में कर सकते है कार्य छोड़ प्रारभ होने के 30 दिनों के बाद 2 आदमियों ने कार्य को पूरा करने में कितने दिन लगेंगे ?
View Solution7 men can complete a work in 12 day. They started the work and after 5 days, two men left. In how many days will the work be completed by the remaining men? e. none of these
View SolutionThree men can complete a plece of work in 6 days. Two days after they started the work, 3 more men joined them. How many days will they take to complete the remaining work?
View SolutionTwenty four men can complete a work in sixteen days. Thirty two women can complete the same work in twenty four days. Sixteen men and sixteen women started working and worked for 12 days. How many more. men are to be added to complete the remaining work in 2 days ?
View Solution24 men can complete a piece of work in 15 days. 2 days after
the 24 men started working, 4 men left the work. How
many more days will the remaining men now take to
complete the remaining work?
View Solution12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work ?
View Solution12 men can do a piece of work in 16 days, then in how many days will 8 men complete the same work?
View Solution15 men can complete a work in 12 days they start the work together . In how many days the total work will be finished when. After 4 days 5 more men join the work.
View Solution5 men can do a piece of work in 10 days. How many men will be required to complete the work in 5 days?
View Solution