Twelve children take sixteen days to complete a work which can be completed by 8 adults in 12 days. After working for 3 days sixteen adults left and six adults and four children joined them. How many
1 3 days
2 2 days
3 6 days
4 12 days
Answer : 3. "6 days" Explanation :Answer: C) 6 days Explanation: From the gi
Related Solutions
16 children can complete the work in 12 days, whereas 6 adults take 16 days to complete the same work. This work is started by 16 adults and after 3 days. 10 adults left the work, then, 4 children joined the work Accordingly, in how many days the remaining work get complete?
View SolutionTwelve children take sixteen days to complete a work which can be completed by eight adults in twelve days. Sixteen adults started working and after three days ten adults left and four children joined them. How many days will they take to complete the remaining work ? b. c. d. e. none of these
View Solution16 children take 12 days to complete a piece of work, while the same work can be done by 6 adults in 16 days. The same task was started by 16 adults and after 3 days, 10 adults left it. Then 4 children joined it. Accordingly, in how many days will all of them take to complete the remaining work?
View SolutionTwenty four men can complete a work in sixteen days. Thirty two women can complete the same work in twenty four days. Sixteen men and sixteen women started working and worked for 12 days. How many more. men are to be added to complete the remaining work in 2 days ?
View Solution15 men can complete a work in 24 days and 12 children in 60 days. 10 men started the work and after 12 days 12 children joined the work. In how many days will the remaining work be finished?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View SolutionTwelve men can complete a work in 8 days. Three days after they started the work, 3 more men joined them. In how many days will all of them together complete the remaining work ?
View Solution14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View Solution12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work ?
View SolutionA work can be completed by 3 men in one day. same work by 8 women 3/4 is completed in a day or the same work can be completed in half a day by 18 children working. If 3 women and 3 children are employed for a day, then for how many days should a man be employed to complete the work?
View Solution10 women can complete a work in 7 days and 10 children take 14 days to complete the work. How many days will 5 women and 10 children take to complete the work?
View Solution10 महिलाये एक कार्य को 7 दिनों में पूरा कर सकती है और 10 बच्चे 14 दिनों में एक कार्य पूरा करते है। 5 महिलाओ और 10 बच्चो को यह कार्य पूरा करने में कितने दिन लगेंगे ?
View Solution12 men can complete a project in 20 days. 18 women can complete that project in 16 days and 24 children can complete it in 18 days. 8 women and 16 children leave after working for 9 days. In how many days will 10 men complete the remaining work?
View SolutionA work which 12 men can complete in 8 days can be completed by 16 women in 12 days. 16 men started working and after 3 days 10 men left and 4 women joined. In how many days will it take to complete the remaining work?
View Solution12 men can complete a work within 9 days. After 3 days they started the work, 6 men joined them to replace 2 men. How many days will they take to complete the remaining work?
View Solution12 men can do a piece of work in 90 days. After 30 days from the start of the work 2 men left the work and 8 men joined. In how many days will it take to complete the remaining work?
View SolutionA' completes a work in 12 days 'B' completes the same work in 15 days .A started working alone and after 3 days B joined him .How many days will they now take together to complete the remaining work ?
View Solution‘A’ completes a work in 12 days. ‘B’ completes the same work in 15 days. ‘A’ started working alone and after 3 days B joined him. How many days will they now take together to complete the remaining work?
View Solution