Two persons can complete a piece of work in 9 days. How many more persons are needed to complete twice the work in 12 days ? a 3 b 2 c 4 d 1
Correct option d 1Explanation:By putting the value in formula as given in question no. 71.Let N persons are needed to complete the work. According to Question After solving N = 3 men More man needed = 3 – 2 = 1 man
Related Solutions
Two persons can complete a piece of work in 9 days. How many more persons are needed to complete double the work in 12 days?
View SolutionTwo persons can complete a piece of work in 9 days. How many more persons are needed to complete double the work in 12 days?
View SolutionTwo persons takes 9 days to complete 2 work. To complete double of that work, in 12 days how many more persons will be required?
View SolutionSome persons can complete a piece of work in 84 days. In how many days will twice the number of these persons complete half of the same work?
View Solution12 persons can complete half of a work in 9 days. How many persons can complete the same work (whole) in 6 days?
View SolutionTwo men take 9 days to complete a piece of work, how many more men will be required to complete twice the work in 12 days?
View Solution14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ?
View SolutionA and B together can complete a piece complete a piece of work in 12 days , B and C together can complete it in 15 days. If A is twice as good a workman as C, in many days will A alone complete the same work ?
View Solution20 persons completed rd of the work in 12 days. How many more person are required to finish rest work in next 12 days?
View Solution360 men can finish a work in 20 days. How many persons will complete 1/2 of the work in 12 days?
View Solution15 persons can do a piece of work in 12 days. How many more people are required to complete the work in 10 days?
View Solution20 persons completed of the work in 24 days. How many more person are required to finish the rest of the work in next 12 days?
View SolutionIf 24 men work 8 hours a day can complete a piece of work in 18 days, then 36 Persons working 12 hours a day In how many days will he complete the work?
View Solution12 persons can do a piece of work in 4 days. How many persons are required to complete 8 times the work in half the time?
View SolutionIf 5 persons can complete a piece of work in 28 days, then the number of persons required to complete the same work in 7 days is
View SolutionA alone can complete a piece of work in 6 days and B alone can complete the same piece of work in 12 days. In how many days can A and B together complete the same piece of work ?
View SolutionMen and 5 women can complete a piece of work in 12 days. 5 men and 2 women can complete the same work in 9 days. In how many days can only 3 women complete the work?
View SolutionA' can do a piece of work in 4 days and B in 12 days. In how many days can A and B together complete the same piece of work ?
View Solution