Doubtnut Promotions Sticky

Two persons takes 9 days to complete 2 work. To complete double of that work, in 12 days how many more persons will be required?

A

2

B

3

C

1

D

4

Text Solution
Verified by Experts

The correct Answer is:B

|
Updated on:21/07/2023

Similar Questions


Knowledge Check

  • Question 1 - Select One

    20 persons completed 13rd of the work in 12 days. How many more person are required to finish rest work in next 12 days?

    A20
    B12
    C18
    D40
  • Question 2 - Select One

    If 20 men take 15 days to complete a certain amount of work working at 10 hours per day, then how many more men are required to complete twice the previous work in 10 days working at 12 hours a day?

    A10
    B20
    C30
    D40
  • Question 3 - Select One

    7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work

    A28
    B21
    C14
    D7